Most public swimming pools in Liège, the Fiery City, had been forced to close in the early 2000s. In 2011, the City of Liège launched a project for a new swimming pool in the Jonfosse district. It opened its doors, pools and baths to the public a few months ago.

Built on the site of a former factory that had become, for a time, half car park and half urban wasteland, the swimming pool comprises three pools, a teaching pool and a leisure lagoon. It also offers public baths, with individual showers and full bathrooms, a tradition dating back to the first half of the 20th century that is now being revived at some swimming pools, notably in Brussels.

Servio a réalisé toute la partie audio et vidéo de la petite salle, ainsi que la mécanique scénique. (Photo : Lino Bennardo)

Daylight floods the swimming pool, which has a metal sawtooth roof. | © bureau greisch / JL DERU, photo-daylight

A distinctive swimming pool

Inside, Jonfosse swimming pool stands out for its contrasting black zones on the floor and walls, signage for people with reduced mobility, and acoustic cellulose coating applied to the upper sections of the walls around the pools. The swimming pool could also have been one of the only ones in Wallonia with stainless steel pools, but budget constraints scuppered the architects’ idea. The pool has, however, been fitted with a drowning-prevention system comprising 14 underwater cameras.

Foundations and structural stability

“The foundations were built using bored piles,” explains Baudouin Schuermans, structural engineer at engineering consultancy Greisch, which worked on all aspects of the project, including structural stability, special building services and energy. “But when we calculated the quantities of concrete used, we quickly realised that the drilling had broken through into galleries, allowing the concrete to flow away. We therefore had to use casing piles to avoid losing concrete. In addition, the groundwater encountered during foundation excavation was higher and more abundant than expected. Soil contamination, as the previous occupant was a gasworks in the literal sense of the word, also meant that excavation was required, creating additional volumes at foundation level. These spaces have not yet been assigned a use. We also had to take account of the filters used for the swimming pools, which resulted in different height requirements on the lower floors of the building. For structural stability, however, we were able to rely on a wall of reinforced concrete columns from the former factory along one side.” And this swimming pool, which is also topped by a 173-space car park, certainly needed to be structurally stable, if only to support more than 1,000 tonnes of water at a time…

Dans la salle de concert, un système de perches permet de suspendre les éléments de décor en configuration théâtre. (Photo : Servio)

The swimming pool comprises three pools, including a 6-lane semi-Olympic pool, a teaching pool and a leisure lagoon. | © bureau greisch / JL DERU, photo-daylight

Energy consumption

The new swimming pool is equipped with micro-perforated ducts that ensure continuous airflow and a constant temperature throughout the building. This approach also prevents chlorine from building up in the air.

“The sustainable design approach has helped reduce energy demand by optimising the building envelope while making the most of natural gains through the use of large glazed areas,” Greisch explains. The sawtooth roof also features steel lattice girders on the vertical faces of the sawtooth sections to maximise the amount of daylight entering the building. “A CHP system producing 180 kW of heat and 107 kW of electricity, combined with a heat-pump dehumidification system, significantly reduces the complex’s energy consumption. It is also worth noting the carefully planned separation between the different zones to manage their energy consumption separately. This approach is also reflected in the construction, with 70% of the materials being recyclable.”

The final challenge was the lighting. Everything was modelled in 3D in advance to determine the right angles for each area and avoid dazzling swimmers, particularly when swimming on their backs and during competitions.    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectPublic space
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.