Public space

Bespoke, locally made street furniture

« Toute l’expérience du soudeur est requise pour récupérer ces déformations le mieux possible. Un véritable travail d’orfèvre ! »
« Toute l’expérience du soudeur est requise pour récupérer ces déformations le mieux possible. Un véritable travail d’orfèvre ! »

The redevelopment of public spaces in Verviers is focused on quality. The natural stone paving of pavements and squares is therefore complemented by bespoke street furniture made just 20 km away, at EMSD in Malmedy: 2 large canopies and 5 bus shelters, all cantilevered for a light, airy appearance. Julien Antoine, head of the technical office at EMSD, gives us an insight into these metal structures, which are a true feat of craftsmanship.

For the public space in Verviers city centre, EMSD modelled and manufactured a first canopy in its workshops for place Verte. Installation on site is scheduled for late February to early March. A second canopy, for place du Martyr, is still at the design stage with the architect. EMSD is already working on the bus shelters, which will be located along the rue Xhavée-rue Crapaurue route. Finally, the metal construction company has also produced backrests with LED strips, most of which have already been installed on the planter-benches dotted around the city (see article on pages 142-143).

Elliptical in shape and supported at just 3 points, the canopy at place Verte measures 23 m long by 14 m wide.

4,000 hours of work in fabrication alone 

Julien Antoine: “Based on the 2D plans from Greisch, which reflect the architect’s requirements while incorporating stability considerations, we created a 3D model of the entire structure and all its components. We adapted certain elements to meet the constraints of fabrication and installation. Quite a job!”

The rectangular bus shelters are open on all 4 sides to allow easy access for people with reduced mobility.

Elliptical in shape and supported at just 3 points, the canopy, 23 m long and up to 14 m wide, comprises a glazed central core and 16 blades made of untreated steel, metallised and painted aluminium grey with a subtle mirror effect. Recessed between the blades, an LED strip adds a lighting effect. Julien Antoine: “Although each blade’s underside is made up of numerous welded sheets, it must be perfectly smooth. To ensure the structure is rigid, we use transverse and longitudinal stiffeners concealed inside the canopy. As the heat from welding causes slight deformations, which could result in rippling around the stiffeners, the welder’s full experience is needed to correct these deformations as effectively as possible. It’s a true feat of craftsmanship.”

EMSD also produced backrests with LED strips, most of which have already been installed on the planter-benches dotted around the city.

At place Verte, the new structure will be installed where a conventional rectangular canopy once stood, which has since been demolished. The two-part core and 16 blades will be transported to site and assembled using bolts. To ensure the structure is watertight and durable, a specialist contractor will then apply EPDM and liquid resin across the entire upper surface of the canopy.

Second canopy and bus shelters unveiled

Although Julien Antoine does not yet have the information needed to begin modelling, he has already revealed a little about the canopy that will be installed at place du Martyr once it has been paved: “This canopy will be very different, with a design more like that of the bus shelters: positioned beside the Vesdre, cantilevered out towards the square, supported by just 2 columns and topped with a glazed roof…” The rectangular bus shelters come in 2 lengths: 9.5 m and 12 m. They also feature a recessed LED strip and are open on all 4 sides to allow easy access for people with reduced mobility, as the pavements are not wide enough everywhere.

The core of the canopy at place Verte, with its blades and stiffeners, is awaiting trial assembly.

Local production

Julien Antoine: “All our workers live within a 20 km radius of the company. What makes this project particularly rewarding is that the whole team is even more motivated because they will be able to come and admire the structures with family or friends once they have been installed. And take pride in the work they have done!”  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectPublic space
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.