A multidisciplinary metalwork project combining functionality and aesthetics
Texte ALT GROUP et Philippe Selke | Photos ALT GROUP

The redevelopment of Esplanade Batta in Huy is undoubtedly one of ALT GROUP’s three major achievements in the year drawing to a close, alongside Tivoli Hospital in La Louvière and the ZIN NOORD tower project in Brussels.
In recent years, the ALT GROUP holding company has brought together all the operational entities it needs to manage and deliver every aspect of a metalwork project in the building sector in-house.
The project aims to revitalise this square in Huy and return the space to the public, incorporating a distinctly modern architectural touch. Metalwork is a major part of the project, which required the expertise of every entity in the group. It was therefore only natural for ALT GROUP to take on this ambitious project.
Metalwork featured throughout the project, divided into three distinct phases in terms of timing, technical complexity and expertise: steelwork embedded in concrete, conventional metalwork and civil engineering structures (footbridges and metal ramps).

Steelwork embedded in concrete
The architect wanted to create a concrete slab that highlighted its various constituent elements. ALT GROUP therefore installed wide steel strips flush with the slab, creating patterns. These provide not only visual interest but also a variation in texture between the steel, concrete and gravel.
The steel edging to the slabs, which serves as formwork stops, was also treated as a visible architectural feature. Its technical role as formwork therefore had to be combined with an aesthetic purpose in the finished project. A practical function for collecting and draining rainwater was also incorporated, alongside its aesthetic role.
To meet these various objectives, it was necessary to create a precise 3D model of all the elements (strips, slab edges, drainage, structural steel and concrete), taking account of the different slopes and flush finishes in the concrete to ensure perfect installation.
Conventional metalwork
The project also included a more conventional phase of metalwork in an urban setting. This involved slab-edge guardrails, handrails and stair rails, as well as access gates for the goods lift. These elements were made by Joiret and Ferinox, entities within ALT GROUP specialising in metalwork for businesses and private clients.

Civil engineering structures
The final and central part of this project was the construction of the footbridge spanning the road and the ramps leading to the towpath along the Meuse. To achieve the architect’s desired result while ensuring long-lasting corrosion protection, these elements were designed in two stages. A load-bearing structure made from hot-dip galvanised steel tubes provides stability. It is then clad in black powder-coated sheet metal to achieve the desired seamless appearance. A special anti-slip coating was used on the pedestrian surfaces.
Making the joints and fixings as discreet as possible required the utmost precision from the fabrication and installation teams. The forms and volumes specified by the architect left no margin for error in the cladding sheets. Here too, collaboration between the teams at ACJB, ALT, Technolac and Lardinois worked wonders. The result is simply stunning. The finished ensemble is a genuine architectural success and a technical feat in its execution.

Functional and aesthetic
The finishing touch to the project is the installation of mirror-polished « alucobond » sheet cladding beneath the promontory overlooking the Meuse. The sheets brighten the space beneath the promontory by reflecting the water and the collegiate church, much to the delight of passers-by. The interplay of light and shadow here is well worth seeing.
It is remarkable that each of these metal elements has been given an aesthetic role in addition to its usual practical function.
This project shows that the metalwork in a project cannot be reduced to joining and welding steel beams or tubes. The scope of the work is extensive and varied, and requires a broad range of technical knowledge. That is why it calls for multidisciplinary expertise and experience. ALT GROUP brings all of this together through its various entities. This is its raison d’être and added value, and is essential to the success of projects such as Esplanade Batta and many more in the future.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectPublic space