A cycle and pedestrian bridge with more to it than meets the eye

Texte Philippe Selke | Photos Techno Métal Industrie

Immaculée, la passerelle tranche actuellement avec le gris et le vert ambiants. (photo : Eriges 2023 | S. Schmitt – Global View)
Immaculée, la passerelle tranche actuellement avec le gris et le vert ambiants. (photo : Eriges 2023 | S. Schmitt – Global View)

The Seraing valley is undergoing a major revival, with a host of landmark projects set to make it a new focus of activity. A 180 m cycle and pedestrian bridge, designed by AgwA and engineered by structural engineering consultancy Bollinger+Grohmann, then built by steelwork contractor Techno Métal Industrie (TMI) of Andenne and installed with its client Batitec, will soon link the former Ateliers centraux, currently being redeveloped, to Parc de Trasenster on the banks of the Meuse. Straight in design, it conceals considerable complexity, as Arnaud Tourny, project manager at TMI, explains.

The section spanning the railway tracks was installed overnight one weekend in May, during a planned service interruption by Infrabel.

Funded by the European Regional Development Fund (ERDF), alongside the redevelopment of Ateliers centraux, at a total cost of 5.26 million euros, with support from Wallonia and Liège Europe Métropole, the bridge is accessible to people with reduced mobility (PRM). It is designed as a dynamic, landscape-led interchange linking the upper part of the neighbourhood, the park, Ougrée station and the surrounding streets.

The bridge is 3.5 m wide, extends for more than 180 m and reaches a height of 7.10 m. It is accompanied by a 60 m ramp and a 20 m staircase serving both sides of Ougrée station. Arnaud Tourny explains: « Its distinctive feature is that it is built around a central post (31 in total), welded on site to a 1.5-tonne solid steel crosspiece that supports the longitudinal beams on either side. These were delivered to site in several sections, up to 21 m long and weighing 11 tonnes each for those spanning the railway tracks. The bridge used 140 tonnes of steel in total, excluding the deck. » As the components were too large to be galvanised, they were metal-sprayed and then given a three-coat paint system. Workshop production involved 5,100 hours of work, including 2,400 just for making the parapets.

Because of their width, many components left the workshop by abnormal-load transport for delivery to site.

The beams spanning the railway tracks are statically indeterminate. A certain moment had to be applied to them during on-site welding so that, when the stresses were released before concreting, they would act as a single element with the adjacent beams. In addition, to prevent them from dropping too close to the overhead wires once the deck had been poured, the precamber applied in the workshop had to be maintained until concreting. This section was installed overnight one weekend in May, during a planned service interruption by Infrabel. In such cases, the work must be completed in a single operation, which calls for thorough advance preparation.

To prevent the beams from dropping too close to the overhead wires once the deck had been poured, the precamber applied in the workshop had to be maintained until concreting.

The complexity is in the details

So what was it about these parapets that made them so labour-intensive? Arnaud Tourny explains: « The architect had a very clear idea of what they wanted, which gave us a real challenge. The uprights had to be evenly spaced and fitted with 40 x 40 mesh. But the horizontal wires had to remain level, whatever the bridge’s incline. This led to a lot of offcuts in the workshop, where each wire was welded to the frame, point by point. As every mesh panel was therefore unique, installing them on site required great care. »

Another architectural detail was a stainless-steel canopy with a polished mirror finish on its upper face, positioned on both sides of the deck where it crosses the railway tracks. While canopies of this kind avoid the need to raise the parapet at this point for safety reasons, the mirror finish was a first for TMI. Arnaud Tourny explains: « We assembled the various mirror-finish components using stiffeners, and the welds obviously had to be as inconspicuous as possible. To ensure a uniform finish throughout, the assembly was sent to the Netherlands for treatment ».

Making the parapets to the architect’s specifications proved a real challenge..

The hollow handrails are fitted with LED lighting along their entire length. To make it easier for the electrician to install the power supply, TMI provided draw wires at regular intervals. Only a few finishing touches remain before the bridge can be handed over, to the pride of the people of Seraing. 

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectPublic space
Share this article

Advertisement

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.