Time-lapse: upgrading the Ampsin-Neuville lock complex

In September 2018, work to upgrade the Apmsin-Neuville lock complex was officially launched. SOFICO invites you to follow the progress of this colossal project in pictures by watching its six-monthly time-lapse!
Since 2018…
• The main structures of the future upstream and downstream bank walls, made of secant piles, have been built.
• Earthworks for the artificial river fish pass are under way.
• Work is initially focused on the small lock, which has been demolished (55 x 7.5 metres). The walls of the future lock (225 x 112.5 metres) have been built on the Meuse side. This lock (225 x 112.5 metres) is expected to enter service in the second half of 2021. It will allow navigation to continue while the large-gauge lock (225 x 25 metres) is being built, with commissioning expected by the end of 2023.
More information about this project is available here: Ampsin-Neuville lock | Sofico
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeTransforming infrastructure and territories
- SubjectProjects