The remarkable challenge of fitting a hotel inside a factory that is still operating

The Pegard hotel has just opened its doors in Andenne. What makes it unusual? It occupies the left wing of a factory that is still in operation, namely Pegard Productics, a company that has been active in machine tools and precision machining for nearly a century. Architecture practice BSolutions, backed by its engineering teams, BURO 5, responsible for the interior design, and main contractor Picard Construct all played an active part in this original project. The result gives the site a new purpose without erasing its character, while making the original building’s industrial function easier to read.
Pegard, a company established in 1937, has taken the bold step of converting part of its premises into a hotel complex with an industrial design. It was a unique opportunity to breathe new life into these spaces while preserving their historic and industrial character. “The project grew out of the need to increase activity at our company’s historic site while maintaining and developing our core business of machining,” says the Pegard website. “We therefore had to find an activity that could coexist with industrial operations in a town centre.”

A hotel shaped by the history of the site
“Unlike standardised, impersonal hotel chains, the hotel offers an unusual setting, bringing together a working factory and visitor facilities including a business centre, meeting rooms and bedrooms,” explains Guillaume Delstanche, the architect leading the project at BSolutions. “It stands out for its unprecedented and highly symbolic character, helping to tell the industrial story of the City of Andenne. Our teams helped make this rather audacious challenge a reality: combining precision machine tools with the comfort of hotel rooms. Our architecture department, which specialises in industrial projects, and our entire engineering division delivered the project to the agreed timetable. BSolutions also incorporated its collaborative BIM by BSolutions approach into the design.”
The key challenge was to strike the right balance between the site’s industrial past and the client’s ambition to provide guests with all the comfort expected of a 3-star hotel. “
“The building’s refurbishment therefore draws on the site’s history, with industrial features such as machine parts, the factory’s red brickwork and a still-operational goods lift. Guests also enjoy an unobstructed, fully soundproofed view of the working factory.”

A sustainable, circular coexistence
In a clear example of innovative thinking, sustainability and environmental considerations were also studied in detail. Guillaume Delstanche explains: “The conversion of the existing buildings, which initially seemed to be one of the main environmental constraints, ultimately became the project’s driving force. The renovation works improved the building envelope by insulating the façades and applying a render, enhancing both the building’s energy performance and its contemporary appearance. This was complemented by short supply chains, the reuse of materials and furniture, the hotel’s links with the town centre and the promotion of local products.”

Safe and responsible coexistence
Picard Construct was responsible for the structural works and finishes, with support from several subcontractors. Antoine Urbain, project manager at Picard Construct, highlights some of the key aspects of this project, which lasted just over a year. “We had to carry out the works alongside the factory’s operations. This required precise day-to-day management of deliveries, sealing off the site and minimising noise for the factory workers. The work included bringing the building’s structure up to fire safety standards, installing fire-resistant compartmentation between the factory and hotel, completing the shell and core, and fitting out the hotel in line with acoustic requirements. The architectural choices called for materials that reflect the factory’s activity. These include Corten steel cladding on the factory’s front façade beside the hotel entrance, and a poured terrazzo resin floor in the breakfast room.”
Question about this story? Ask your question
Who worked on it
- ClientEalïs Immo
- ArchitectsBSolutions Architectes, BSolutions Ingénierie, BURO 5
- Main contractorPicard Construct
Keep following this