The MAP, a building like no other, including for the general contractor

Avec le bois, on a pu utiliser des machines plus petites, plus légères et plus rapides qu’une grue-tour traditionnelle.
Avec le bois, on a pu utiliser des machines plus petites, plus légères et plus rapides qu’une grue-tour traditionnelle.

The Maison Administrative de la Province de Namur (MAP) was featured in an article in this same magazine a few months ago. An exemplary building, remarkable for its shape and construction model, with timber taking centre stage. The project also brought its share of new challenges for general contractor Jan De Nul, despite its extensive experience in major construction projects and collaboration with Philippe Samyn and Partners srl.

The general contractor started with a relatively straightforward, streamlined specification, containing mainly the requirements while leaving considerable freedom in terms of specialist systems, environmental performance and materials. “The architect wanted the building to be demountable and modular, which is made possible by the 8 rectangular courtyards that make up the project,” explains Nelson Moors, project manager at general contractor Jan De Nul. “The building also had to be raised, to limit the risk of flooding and allow rainwater to infiltrate the ground more easily.” This was a deliberate choice, but also an economical one: “We tried to disturb the natural contours and ecosystem as little as possible,” Philippe Samyn explained a few months ago. “With the help of numerous engineering consultancies, we analysed the ‘genius of the place’, the specific characteristics of the site, which enabled us to build as economically as possible.”

The MAP, an exemplary building, remarkable for its shape and construction model, with timber taking centre stage.

Timber instead of concrete

A general contractor is more accustomed to working with concrete. But here, there is no concrete, just a timber frame, a real feat for a building of this size, just over 10 000 m², with spans of this length. Nelson Moors: “Building in concrete requires a great deal of handling. With timber, we were able to use smaller, lighter and faster machines than a conventional tower crane. Working with a prefabricated, enclosed structural frame also called for different assembly techniques, which were simpler and quicker. With timber, once the roof is in place, the building is watertight and dry. This saves quite a lot of time during the finishing phase, as there is no drying time. We do not core-drill concrete, we use less water and generate less dust. Cutting timber is simpler, and most of the cuts had even been planned during prefabrication. Air quality on site was better, and we could feel the difference compared with a concrete building, which is harsher, colder and damper.” 

The window frames were installed on site to ensure that the windows were perfectly aligned.

A strong and effective partnership

“For this project, we had to find a partner capable of providing a technical solution and manufacturing all the components within the allotted time.” That partner was Mobic. “Together with the Philippe Samyn and Partners srl practice, we adapted the original proposal, which involved installing steel beams spanning 12 m between the façades and the courtyards. The beams crossing the floor made it difficult for machinery to pass through and for materials to be delivered and stored. With Mobic, we switched to a standard continuous floor system from the outset, without any obstacles. The steel beams were therefore replaced with timber beams, which were more numerous and deeper because timber is less strong than steel. These are trussed beams, in other words built-up beams made from small timber sections joined together to form a long beam, enabling them to span 12 m and bear the required loads. An OSB floor was laid directly on top to create this continuous floor.” 

Beams, façade frames, cladding… everything was prefabricated in the workshop, except for the OSB floor and the window frames. As for the latter, “given the tolerances of timber, it was too risky to install them during prefabrication, as the façades might not have been perfectly aligned,” explains Nelson Moors.

The MAP, a prefabricated building made primarily of timber, with a remarkable natural ventilation system, is certainly not a building like any other, whether you are a designer, builder or occupant…  

Question about this story? Ask your question

Who worked on it

  1. ClientProvince de Namur & BEP
  2. ArchitectPhilippe Samyn and Partners srl, architects & engineers
  3. General contractorJan De Nul nv

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectProjects
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.