Waterways have always been vital links in economic life. As technical and environmental requirements continue to evolve, SPW Infrastructures and SOFICO have in recent years considered upgrading several locks on the Meuse between Namur and Liège to accommodate larger vessels. This is currently the case at Ampsin-Neuville, where Franki Foundations has been commissioned to carry out the foundation works.

In Belgium, nearly 160 million tonnes of goods are transported by waterway each year. This volume is continually increasing, causing mobility problems and lengthy waits at locks. The works are intended to allow larger vessels to navigate the river and pass through its locks.

Commissioned in 1958, the Ampsin-Neuville lock is the 3rd busiest site in Wallonia. Its widening and modernisation are being carried out in two phases: one of the existing locks (55 m x 7.5 m) is being replaced by a 225 m x 12.5 lock, followed by the replacement of the other lock (136 x 16 m) with a 225 m x 25 m lock. Work began in August 2018 and is expected to be completed in 2024.

It is quite unusual to work below the level of the river.

Foundation works: piles and tiebacks

Considerable foundation works were required to reinforce the banks and lock walls ahead of their renovation. Franki Foundations was responsible for this important stage as a subcontractor to the Duchêne, Franki joint venture.
“Our task was to install all the piles for the future banks at the entrance and exit of the lock, upstream and downstream,” explains Benoît Lechien, Site Manager at Franki Foundations.
“We installed 86 piles in the lock and 701 piles for the bank downstream of it.” These are large-diameter secant pile walls (1300 mm), averaging 10 m in depth, adjusted to the depth of the shale. “We also installed temporary piles in the lock to secure the site and allow the new structure to be built. These piles support embankments that hold up the sheet piles, which prevent the Meuse from flooding the lock during the works. Some of these piles will be removed once the works are complete.”

“Following the design work carried out by our engineering department,” continues Benoît Lechien, “we incorporated tiebacks anchored into the shale. The piles are vertical, while the tiebacks are inclined at between 30° and 90°, allowing them to support the piles and vertical walls by taking the loads acting on them.” Once the lock is flooded, the structure will be self-supporting and the anchors used to secure it will no longer be needed.

Dans sa carrière d’Aisemont (Fosses-la-Ville), Carmeuse produit des granulats mais aussi de la pierre calcaire très pure.

Large-diameter secant pile walls were installed to an average depth of 10 m.

Site challenges

Franki Foundations is experienced in this type of work and in concreting underwater. In 2018, the company built bank walls on the Scheldt at Tournai. However, Benoît Lechien acknowledges that this large-scale project is certainly complex, particularly because of the considerable movement of machinery. “There are a lot of factors to take into account. Working on the banks with small anchoring machines requires quite a lot of planning, both in terms of safety, especially for the workers in front of the machines, and equipment,” he says. “It is also a challenge for the client to meet our requirements: we use machines weighing around a hundred tonnes, so we need a stable platform with access for lorries and other machinery. This required a great deal of preparatory work with the client, followed by close monitoring to ensure we could work day by day, in any weather and in any situation.” If all goes to plan, this part of the project should be completed in February 2021.    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeTransforming infrastructure and territories
  • SubjectProjects
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.