Planning permit granted for structure at brussels-north station

Another major milestone for the Metro 3 project. A planning permit has been granted for the construction of a metro tunnel beneath the…
Another major milestone for the Metro 3 project. A planning permit for the construction of a metro tunnel beneath the railway tracks at Brussels-North Station was granted by the Brussels-Capital Region on 25.05.2020. The planning permit application was submitted on 18 August 2017 by Beliris, the project owner acting on behalf of STIB.
In addition to the planning permit just granted, the environmental permit was issued on 3 July 2019. Local residents were consulted as part of the impact assessment, which took place from 1 May 2018 to 17 January 2019. These permits for the construction of a metro tunnel beneath the railway tracks at Brussels-North Station mark an important milestone for the Metro 3 project, as the tunnel will enable the first section of the line between Brussels-North Station and Albert to enter service.
« Preparatory works began at the end of January 2020 on the rue du Progrès side, with the relocation of underground utility networks. Asbestos removal and the demolition of an old, vacant building belonging to Infrabel are under way to prepare the site for the future works. The civil engineering works to build the tunnel beneath the railway tracks should then be able to start in the final quarter of 2020 », explains Cédric Bossut, Director of Beliris.
The structure at Brussels-North Station will serve two purposes. « Initially, the section where Metro 3’s tunnel passes beneath the railway tracks will serve as a reversing facility, allowing Metro 3 to carry out the necessary turnback manoeuvres when the Brussels-North Station-Albert section enters service. In the long term, it will become a section of tunnel and carry Metro 3 services along the entire Bordet-Albert line », explains Brieuc de Meeûs, CEO of STIB.
The Metro 3 project
The future Metro 3 line will add a new 10.3-kilometre axis to the metro network, linking Bordet and Albert stations in just 20 minutes. The Metro 3 project is being delivered in two phases.
The first phase involves converting the premetro into a metro between Albert and Brussels-North Station, as well as building the new Toots Thielemans station.
The second phase involves extending this section as far as Bordet by building a 4.5 km tunnel, 7 new, modern stations and a depot.
The project, led by STIB and Beliris, is a partnership between the federal state and the Brussels-Capital Region. Its aim is to improve public transport mobility, quality of life and liveability in the capital.

The Metro 3 partners
STIB is building the infrastructure needed to convert the premetro into a metro on the existing section between Albert and Brussels-North Station. It is defining and ordering the new metro trains, equipping the structures for operation (tracks, safety systems, etc.) and acquiring the land required. It will also operate the line in the future.
Beliris, the Brussels public project owner, makes its expertise available to the Region to deliver the new infrastructure, including the passage beneath Brussels-North Station, a new tunnel and the stations on the extension from Brussels-North Station to Bordet, specialist systems and station fit-out, as well as the future metro depot in Haren. Beliris also oversees the studies and permits in close consultation with the Métro Nord design office.
The Brussels-Capital Region is delivering the conversion of the 10 existing stations and infrastructure, as well as the surface-level works, through STIB and its regional administration, Bruxelles Mobilité.