Multimodality arrives at the station in Wallonia’s capital

They say that everything takes a little longer in Namur… Started in 2016, this mammoth project is finally reaching the station, a few years behind schedule. Despite numerous constraints and unpleasant surprises, including unstable ground, COVID and flooding, the integrated joint venture Franki-Duchêne is about to deliver a unique complex that will be of great service to everyone passing through Wallonia’s capital, within a budget whose increase has remained reasonable.
Divided into several zones and phased, in particular to keep road and rail traffic running, the project involved strengthening and extending the existing railway station structure, building a bus station above it with a cable-stayed bridge for access, modifying the access roads and renovating the interior of the existing station.
Manuel Nemes, Head of Civil Engineering at Duchêne: “This is one of the largest civil engineering projects Duchêne has ever completed. The whole complex will be finished by the end of this year, with just a few works remaining on the Chiny wing.”

A spectacular new bridge in the city centre
The first phase involved relocating the existing bus station by building temporary roads and platforms (23 000 m2). On the site of the former bus station, an 80 m span cable-stayed bridge with a 190 m ramp was built to give buses access to their new station on the roof of the railway station, directly from the Léopold roundabout. Manuel Nemes: “Getting started was complicated because we had to deal with technical constraints affecting the foundations, due to ground containing karst areas that could compromise stability. For example, we had to extend the foundations considerably to support the bridge. The piles were increased from 18 to 26 m, and we then drilled down to a depth of 36 m to check for cavities. We also had to take account of existing underground structures carrying a watercourse.” Built as a steel-concrete composite structure, the bridge is not only curved, its pylon is also inclined and simply supported. The deck of its access ramp rests on more than 200 white concrete columns.

Buses above the trains
Next came the construction of the bus station on the second level of the existing SNCB station slab (12 000 m2). 1050 m2 of curtain walling with laminated glazing was installed. A fairly complex steel frame supports a 5000 m2 photovoltaic glass roof, made up of cells rather than panels, which was quite innovative when the project was designed. These works obviously had to be carried out while keeping the railway station operational.
Manuel Nemes: “Even to install the façades, we had to work to fixed schedules, depending on track closures planned well in advance.”
SNCB took advantage of the works to renovate the interior of the railway station: the suspended ceilings and floor tiles were replaced, as was the entire façade (4000 m2 of curtain walling), which until recently had only been enclosed with temporary structures… A new police station was built in place of the old one. The Chiny wing, on the right of the existing building, is still being refurbished to make it one of the main entrances to the bus station. Manuel Nemes: “A small contribution to the project, but one that took a great deal of effort because of the building’s instability, forcing us to adapt our demolition and rebuilding methods.”

A project successfully completed
Manuel Nemes: “We were hit by the COVID crisis, which brought some of our supplies from abroad to a standstill, followed by the floods in summer 2021, when the building was not yet fully watertight. Soaring prices and supply problems made managing such a major project more difficult, but we got there!”
The various facilities have been brought into service as the work has progressed. The bridge and TEC offices are already operational. Buses are parked on the deck without passengers, and users should be able to access it very soon.
Successfully completing a project of this kind in such a busy urban environment posed a major challenge for the contractor, but the work helps put Wallonia’s capital on the multimodality map, which is essential to the future of our cities.
Question about this story? Ask your question
Who worked on it
- ClientEurogare S.A
- ArchitectNEY and Partners
- Main contractorSM Franki: Duchêne