Florennes municipal swimming pool: energy-efficient and comprehensive renovation thanks to the Swimming Pool Plan
Texte Philippe Selke Photos Philippe Piraux

The renovated Florennes swimming pool was officially opened a year ago, following two years of work. The Wallonia Swimming Pool Plan enabled the municipality to benefit from a high-quality facility, with the project design entrusted to Intercommunale INASEP, which specialises in water-related matters. Energy performance, comfort and aesthetics were all priorities, as David Windels, Head of ARTENCO, INASEP’s building consultancy, explains.
Like many swimming pools in Wallonia, the Florennes pool, built in the 1970s, was in a poor state and no longer complied with current standards. The insulation, filtration and heating systems were all in a lamentable condition. It even rained in the changing rooms…
Comprehensive renovation
David Windels: “The renovation of the Florennes swimming pool is one of a series of projects put out to tender by INASEP in the Province of Namur under the Wallonia Swimming Pool Plan. Couvin was the first to be completed, in late 2022, followed by Florennes in early 2023. It is a fine achievement on a fairly complex project, involving several work packages that had to be coordinated, but everything went well.”
“The major advantage of the Swimming Pool Plan is that it enables the entire building to be renovated. We therefore renewed the thermal envelope and building services, including a heat pump and heat-recovery ventilation, and even added a cogeneration system.”

Energy-efficient renovation
A small leisure pool for young children, heated to 31 degrees, was built alongside the 25-metre main pool. Maintaining different water temperatures required precise control of the heating system.
The pool area and changing rooms are now ventilated separately. A perforated duct runs around the pool, achieving an air change rate twice the standard requirement. System controls are now highly precise, both to ensure comfort in the different areas and to monitor energy consumption accurately. David Windels: “The provisional acceptance a year ago was followed by a two-year commissioning period to verify system performance and improve it where necessary. We have in-house specialists to provide consistent technical monitoring and maintenance for the various pools in operation.”
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeRenovating existing buildings
- SubjectProjects