Dismantling a motorway viaduct while it remains in service: safety and method

Anyone travelling on the E42 motorway between Namur and Liège cannot fail to notice the ongoing refurbishment of the Huccorgne Viaduct near Wanze. This 50-year-old concrete giant stands 60 m tall, and its huge refurbishment project has been awarded to the BAM Galère, BESIX joint venture by SOFICO and SPW Mobilité et Infrastructures. Eloy Group’s Demolition team is currently on site as a subcontractor, carrying out work where urgency must not be confused with haste…
Although Eloy Group’s Demolition team has gained experience through numerous projects in recent years, dismantling a structure of this scale remains an exceptional undertaking requiring equally exceptional supervision.

Safety: zero tolerance
Alongside the technical challenges, safety is the number one priority here. Charles Maquet, site manager for Eloy: “We first had to prove to our client that we could meet all its requirements, both for safety and for methodology. To do so, we worked with our entire Demolition team to establish rigorous procedures. Every person working on site must sign a toolbox talk form before being allowed access, reminding them of the safety rules specific to this project. The aim is also to maintain a stable team of highly qualified workers throughout the project, with Eloy able to draw on its specialist demolition staff.”
A Herculean task… in 6 weeks
The extremely tight schedule is a second challenge. Eloy was awarded the contract in early December and started work on 10 January, with completion due by 15 February at the latest! The work involves laying a crash bed beneath the viaduct (3,400 t of recycled material), then making several openings in the deck to install stabilisers before demolishing it (2,000 t of concrete), and finally diamond-wire sawing and lowering the 60 t main beams so they can be crushed on the ground… all in 6 weeks! This first phase covers the carriageway towards Liège, with traffic diverted onto the lanes towards Namur. The contract provides for the same work to be carried out in the opposite direction a year later, provided the current work meets expectations.
Charles Maquet: “Even though the schedule is tight, the watchword is not to create unsafe conditions by applying too much pressure. Everything is going very smoothly. What’s more, seeing the good overall condition of the sections we have started dismantling makes me less concerned about encountering reinforcement bars that have been overstressed.”

Machines and people
In practice, around ten workers are on site at all times, working with 6 machines, including 4 25 t excavators fitted with crushers. They work 10-hour days, including a few Saturdays. The most spectacular phase is planned for the end of the project: the main beams will be diamond-wire sawn, lifted out by Galère-BESIX using cranes with capacities of 800 to 900 t, then crushed on the ground by Eloy using 40 t excavators and 1.5 t crushers. All demolished concrete will be sent to Eloy’s recycling centre in Bierset. Once crushed, it will be used either as sub-base material or as fine aggregate for the concrete plant. The steel will be separated and sent for recycling too.

A viaduct worthy of the Eloy ethos
Charles Maquet: “This project is a good reflection of the Eloy ethos because it has required a fair amount of ingenuity and teamwork to develop the methodology and meet all the safety standards. I would like to thank Eloy’s management for the confidence they have placed in the team. Eloy has the equipment, people and expertise to complete this mission successfully. But on a project like this, it is best to leave nothing to chance…”