Despite several setbacks, a handsome car park delivered on time

Réalisé en Design & Build, le bâtiment apparaît presque aérien grâce à un bardage métallique gris clair.
Réalisé en Design & Build, le bâtiment apparaît presque aérien grâce à un bardage métallique gris clair.

A car park with 866 spaces across 7 levels was built on the Erasme site in Anderlecht alongside the new Institut Jules Bordet. Delivered under a Design & Build contract, with Art&Build responsible for the design, CIT Blaton and In Advance for construction, and Interparking for financing and operation, the building has an almost airy appearance thanks to its light grey metal cladding. Thibault Hendriks, for whom this was his first project as a site manager for CIT Blaton, explains some of the challenges overcome to achieve this result.

As the car park had to open at the same time as the new Institute, the deadline had to be met. Thibault Hendriks: “The timing challenge was compounded by constraints on site organisation, to avoid disrupting or being disrupted by work on the hospital and its surroundings. In addition, the hospital’s small open-air car park had to remain accessible throughout the works, further limiting the available storage space.” The 2 site cranes also had to be installed inside the building itself, using openings in the hollow-core slabs.

“The timing challenge was compounded by constraints on site organisation, to avoid disrupting or being disrupted by work on the hospital and its surroundings.”

In-situ and precast concrete

The building cleverly combines in-situ concrete and precast elements. CIT Blaton’s engineering department calculated everything that had to be cast in situ: foundations, rafts, stair and lift cores, etc. Ergon designed and supplied all the precast concrete, more than 1000 elements in total: columns, floor slabs, hollow-core slabs, landings, …

Clay pockets, flooding and sprinklers

The presence of numerous water-filled clay pockets on the lower half of the site, which could not have been detected in advance, caused some problems when excavating for the pad foundations. Later in the project, the exceptional rainfall in July 2021 complicated the pouring of the polished concrete: “Given the weather, it was impossible to schedule this work. The subcontractors were therefore on standby, ready to step in as soon as a drier spell was forecast.” Finally, it became clear during construction that the car park’s two semi-basement levels still required sprinklers to comply with fire regulations, so a tank that had not been included in the original plans had to be built.  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectProjects
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.