Clinique MontLégia: a team of construction professionals behind the project

Clinique MontLégia: a team of construction professionals behind the project

Built on the site of a former coal mine in the hills above Liège, Clinique MontLégia now brings together the activities of the CHC group’s three Liège clinics. The hospital was designed by Assar Architects in association with artau architectures. Dozens of companies, including some of the largest in Wallonia and Belgium, took part in building this facility, which has more than 800 beds.

Clinique MontLégia is the flagship of a site that already includes a care home and will eventually feature an economic activity zone, buildings for businesses (offices, laboratories and cleanrooms for biotechnology companies), the CHC’s administrative headquarters, an eco-district and various mixed-use projects… but no hotel for patients’ companions, much to the architects’ regret. With just over 700 inpatient beds and around 100 day-hospital places, the clinic will have a capacity comparable to that of the region’s two other major hospital complexes, CHU Sart-Tilman and CHR Citadelle.

vue-aerienne_1-kopieren

Clinique MontLégia was built in the hills above Liège, specifically on the site of a former coal mine.

One eye on the future, one on the past

Clinique MontLégia stands where the Patience & Beaujonc company once operated a coal mine. The site closed in 1929 and lay derelict until the CHC management decided to bring its three Liège hospitals, Saint-Joseph, Espérance and Saint-Vincent, together there. “Building a new hospital offered the best guarantees for patients in terms of accessibility and comfort, as well as for care providers,” the CHC explains. The aim was also to set out strategic priorities for the next 30 to 40 years, in particular by making the most of synergies between the various medical departments. And the circle was complete, as Espérance and Saint-Joseph had once served as dispensaries for workers at the Liège coal mine.

chambre-dhospitalisation-kopieren

The inpatient rooms are designed to look as much like hotel rooms as possible.

Bringing services together, while keeping them separate

According to Pierre Maurice Wéry, associate architect at Assar, “every hospital must reflect the core values of its client.” There was therefore no question of offering the CHC the concept used at CHIREC (Auderghem) or Maria Middelares (Ghent), two other hospitals recently designed by Assar. “The CHC had two requirements that shaped the layout: to distinguish the ‘mother-and-child centre’ from the ‘adult centre’, and to locate inpatient facilities next to medical and technical services. To meet these requirements as effectively as possible, we proposed a design based on juxtaposition. The wings housing the adult care units and the mother-and-child services were kept separate, with the latter positioned alongside another block containing the medical and technical functions. This enabled us to create a medical street linking the care units and the medical and technical services. The different flows through the hospital could therefore be clearly separated.”

salle-dimagerie-interventionnelle-kopieren

A futuristic, high-tech look for the imaging and operating rooms.

A combination of expertise

A project of this scale takes a range of skills across the design team. At MontLégia, the team comprised an architect and project manager for the partnership, responsible for the aesthetics and architectural coherence; hospital designers, bringing their knowledge of this specialist building type; technical architects, contributing their specific expertise in areas such as façades and finishes; and ‘site teams’, based on site and overseeing construction. Pierre Maurice Wéry explains: “Assar’s approach is to tackle every project as a team. A plurality of viewpoints ensures that the finished building matches the original sketch visually and the project approved by the Client conceptually. Our work has truly succeeded if it is invisible to anyone walking through the building. The challenge is to master the complexity, make it seem natural and ensure that the means used remain unseen.”       ◊

Hygiene is crucial

“We made recommendations on lighting, visible technical elements and the products to be used,” explains Alwin Fable, the hospital architect in charge of the project. Hygiene is critical in a hospital. “As hospital designers, we have a significant responsibility for hygiene. The first challenge is to meet the requirements of the medical project. This must be balanced with patient comfort, compliance with a large number of standards, hygiene and the separation of flows. Our contribution is to bring all of this together, creating a pleasant place to be, and one that is as little traumatising as possible for patients, while also providing staff with a comfortable working environment.”

Project specifics

On energy consumption, “the buildings in the white wing, which include the inpatient rooms, are low-energy buildings,” explains Alwin Fable. “They have a thick layer of insulation over an aluminium structure and are clad in ceramic façade panels. The medical and technical block, on the other hand, houses operating theatres and other energy-intensive services. A building of this kind cannot therefore be passive.” It is also worth noting that most of the 24 operating theatres receive natural light.

As for the rooms, “we wanted them to look as much like hotel rooms as possible,” says Pierre Maurice Wéry. “Architects specialising in accommodation helped design the rooms, which we wanted to be compact and comfortable.” They also feature windows with lower-than-usual sill and lintel heights. “We ‘lowered’ the façades so patients could see the activity and life around them, not just the clouds. We also limited solar radiation, which often overheats both the room and the patient.” This approach also avoids the need for external blinds or louvres.

rue-interieure-kopieren

A street links the care units and the medical and technical services.

The main construction challenges

The first challenge was building such a ‘giant’ on a ‘Swiss cheese’ site, riddled with mine shafts and, for nearly a century, all kinds of fill material that had to be sorted. An impressive 2,300 piles were driven into the ground to ensure the building’s stability.

The second was bringing together teams from three hospitals around a shared project. Alwin Fable explains: “During the design phase, we were working with three teams, each with a different approach. Work had to be done upstream to develop a shared vision. The architect can play an important role in this. Staff were able to work at the other hospitals to gain a better understanding of one another and identify opportunities for synergies in the future.”

The third challenge was an unusual one. From the design stage, plans had to include 7 ha of habitat for natterjack toads, a protected species that had to remain on the site.

Problems and challenges are part of every construction project. The key is to address them calmly and thoughtfully, as Pierre Maurice Wéry explains: “One way to rise above problems is to think of the building itself, rather than the client, as the client. If everyone sits on the same side of the table and treats the project as the client, each person’s approach will be in the project’s service.”

With plenty on the horizon in the coming years, both in healthcare (the new Clinique St Pierre in Wavre) and in other areas (the expansion of the Paris office and growth of the Belgian teams), Assar’s architects will continue to apply their distinctive approach to their projects.   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectProjects
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.