CHU car parks stay on track

Exactly one year after work began on the CHU’s new car parks at Sart Tilman, it is time to take stock with site manager Nicolas Haulet. Progress is on schedule and impressive, as is Groupe Eloy’s ability to manage projects on this scale. This landmark project is being delivered under a DBFMO (Design Build Finance Maintain Operate) contract, with Eloy expected to complete its work as contractor in one year’s time.

A quick recap of the previous instalments: work is taking place on 3 separate sites around the buildings of the Centre Hospitalier Universitaire at Sart Tilman. Where ground-level open-air car parks once stretched out, three multi-storey car parks are now rising: P112 to the south, the smaller P109 by the CHU’s main entrance, both with 4 upper floors, and the large P101 to the north, with 1 upper floor. Groupe Eloy is carrying out all the construction work on the first, while its scope on the other two is limited to earthworks and infrastructure, with its partner Democo handling the structural work and finishing. The two contractors are working together in the 6nergy Park consortium, alongside architects Herbiet Grosch Architectes (HGA) and Atelier d’Architecture du Sart Tilman (AAST), engineering consultancy Lemaire (BEL), Semaco, responsible for construction planning, and Optimal Parking Control, which will manage the car parks on a day-to-day basis.

A project staying on track
For a project on this scale, which began just one year ago, it is striking that Eloy has so far managed to keep to the planned schedule, give or take a few days. This is further proof of the excellent organisation at the Sprimont-based company, particularly given that the hospital has remained operational throughout the works. How can this success be explained? A combination of factors: good partners, a small number of contractors on site and, above all, rigorous planning of the work phases, …
The site manager is keeping his fingers crossed, explaining that the project has been relatively spared by bad weather, the pandemic and material shortages. “P109 will be the first to open, in March-April. Democo has nearly completed the structural work and has already installed some guardrails. The resin floor finishes still need to be laid. However, winter conditions could prevent this work from being carried out. Once P109 opens, work on P101 can begin.”
Eloy has currently completed 60% of the structural work on P112. This consists mainly of precast concrete elements supplied by Ronveaux (Ciney), which is also undertaking a large part of the installation in collaboration with Eloy’s teams. “


A night-time operation in the works
One of the project’s standout structures is the access ramp crossing Avenue Hippocrate and leading to the roof of P112. Earthworks and retaining structures have been completed over the past few months to make way for the approximately 30-tonne steel structure, manufactured by TMI, which has been awarded the structural steelwork and metalwork contracts for the various car parks. Made from welded built-up sections combined with standard sections, the bridge deck will be formed from hollow-core slabs with additional precast floor slabs to accommodate its slight curve. Corten steel cladding on both the sides and underside will give it a distinctive finish. Nicolas Haulet: “We will need to close at least one lane to install the shoring towers. Then we will need to close the avenue completely for a very short time to install the structure. We will do this at night to minimise disruption, in consultation with the CHU, as ambulances coming from the south use this road. We are currently discussing with TMI the best way to proceed.” Eloy has already carried out this kind of rapid operation earlier in the project, when the heliport had to be moved slightly to clear the car park footprint. It went ahead to everyone’s satisfaction…
Project details
Client
Consortium 6nergy
Architects
Herbiet Grosch Architectes (HGA) and Atelier d’Architecture du Sart Tilman (AAST)
Main contractors
Eloy travaux and DEMOCO
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.