Projects

Charleroi’s archives are on track

Les grilles à tableaux sont guidées par des rails et pourvues d’amortisseurs pour éviter les chocs.
Les grilles à tableaux sont guidées par des rails et pourvues d’amortisseurs pour éviter les chocs.

For Bruynzeel Storage Systems, the industrial building renovated by the City of Charleroi to house its archives and works of art is an impressive project, both in scale and complexity. Nearly 28 km of electronically controlled, motorised Compactus shelving have been installed, along with 50 picture racks.

Measuring 4 x 4 m, the picture racks are arranged on either side of a central aisle in a climate-controlled room, providing 800 m2 of storage space for works of art. However, the project’s biggest challenge lies with the Compactus systems, which occupy most of the building. Although the shelving installed already offers impressive archive capacity, rails for a further 8,000 m of storage runs have already been laid. 

Some Compactus units are 20 m long and 3 m high, weighing 16 to 18 tonnes when loaded.

Zero tolerance

Some shelving units are up to 20 m long and 3 m high, weighing 16 to 18 tonnes when loaded. The usual standards for laying a concrete floor are simply not sufficient: the rails must be perfectly level, with no tolerance. Bruynzeel lays the rails itself on an epoxy cement bed, which requires a perfectly level slab. That was far from the case in this former industrial building. Eric Devigne, project leader at Bruynzeel, says: “The contractor and our team faced major differences in level that had to be corrected, up to 24 cm! The slab was even cut through in places, and the contractor had to pour new concrete there.”

Installing underfloor heating made the work more difficult, as the pipes could not run beneath the Compactus rails because of the load.  

LED lighting

As the City opted for relatively tall systems, lighting had to be considered. The Compactus units here are fitted with integrated LED lighting. Only the open aisles (out of around 180 in the installation) are lit, with a timer function. The additional cost of this LED system will be recouped in just over 2 years…  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeTransforming infrastructure and territories
  • SubjectProjects
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.