Building and extending 5 car parks at the same time: quite a challenge!

Une durée de chantier de 23 mois est prévue pour le parking P12, destiné au personnel (1 110 places – 5 niveaux).
Une durée de chantier de 23 mois est prévue pour le parking P12, destiné au personnel (1 110 places – 5 niveaux).

In 2016, CHU de Liège issued a call for applications to build and extend 3 car parks at Sart Tilman and extend 2 car parks at the Bruyères site.

The 6nergy Park consortium was selected for this major project. Leading this close-knit, multidisciplinary team is the company ELOY, based in Sprimont, working in partnership with DEMOCO. The aim is to increase the number of available spaces from 2,045 to 3,660 within a year.

Cédric Nils, DBFM (Design, Build, Finance, Maintain*) Manager at ELOY, explains what the project involves: “The three new car parks at Sart Tilman, for staff, patients and people with reduced mobility, share the same construction method: demolishing the existing at-grade car park structures, installing retaining walls, excavating, laying a column-beam-floor slab structure with a compression topping, installing steel access walkways and metalwork, and finally applying resin floor finishes. The car parks at Bruyères are extensions to existing at-grade car parks. The work there will therefore mainly involve roadworks.”

Work will begin with construction of the visitors’ car park, P9 (494 spaces, 5 levels). It will take 13 months.

A major project

Building five car parks at once within a fairly tight timeframe is a huge undertaking. “You don’t often get started on a project of this scale in such conditions,” Cédric Nils acknowledges. Both during the project’s development and its construction, the fact that the sites are operational hospitals had to be taken into account. “Throughout the works, a minimum number of parking spaces must remain available, access to the site must be as safe as possible and emergency vehicle routes must be kept open. The presence of a helipad, an essential part of the site, also calls for specific safety measures.”

Other challenges

On top of that, there is the flow of people regularly using the University’s facilities, as well as other works taking place at the same time on both sites: roadworks, refurbishment of the glass roof and emergency department tower (Sart Tilman), and a new care unit with changing rooms and workshops (Bruyères). “These factors make construction, which may seem straightforward at first from a structural point of view, more complicated, particularly when it comes to supplying structural components,” explains Cédric Nils. Other challenges also arose at the design stage: “The main one was finding a way to reconcile the available areas, level constraints and the minimum capacity required for each car park, whether or not it is a multi-storey structure.” 

Fortunately, the project partners can draw on considerable experience. ELOY has recently delivered, for example, the Verlaine motorway service areas, the multi-storey car park at CHU in Esneux and a landscaped car park for the University of Liège at Blanc-Gravier (Sart Tilman).

Work on P1 (1,105 spaces, 3 levels) will begin as soon as work on P9 is complete.

Effective collaboration, tried and tested

The 6nergy Park consortium includes Optimal Parking Control (car park operator), architecture practices Herbiet Grosch Architectes (HGA) and Atelier d’Architecture du Sart Tilman (AAST), engineering consultancy Lemaire (BEL), responsible for structural engineering and building services, and Semaco, which handles site organisation and planning. Cédric Nils says: “OPC agreed to put its trust in us and take on the challenge alongside some of the ‘heavyweights’ in the car park sector. I’m convinced that this choice paid off, as the operator adapted its way of working to meet CHU’s requirements rather than trying to impose its own.” The architects had worked with ELOY before, on both external and in-house projects. What is more, AAST, as its name suggests, is the local firm and has an almost exhaustive knowledge of the sites. There is also clear complementarity with HGA in terms of architectural approach and urban planning vision. Engineering consultancy Lemaire, meanwhile, had a strong track record in car park projects and a good understanding of the other team members. Since each partner was open from the outset to hearing that its proposal could be improved, this proved to be an excellent collaboration. And everyone will have plenty to do, given the project’s very tight schedule.    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectProjects
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.