At the heart of one of Wallonia’s finest castles
Texte Philippe Selke Photos Province de Liège et TPF Engineering

Located in the municipality of Amay, in Liège Province, Jehay Castle is a listed monument and features on Wallonia’s list of exceptional heritage. The oldest part of the castle dates back to the mid-16th century. Following major works carried out over several years, the estate will once again open to the public from 30 March, although the castle interior will remain inaccessible. TPF Engineering won the public contract awarded by Liège Province for a study and works-monitoring assignment, focusing mainly on stabilising the façades and roof structures.

Jean-Michel Frenay heads TPF Engineering’s Stability Division. He reflects on some of the distinctive features of this one-of-a-kind project, although he has seen others over the course of his long career: “When I was young, I worked for another consultancy on Brussels City Hall and the collegiate church of Saint-Guidon… However, Jehay Castle is a unique case in TPF’s portfolio. Restoration projects on this scale are usually carried out as budgets are extended, as has been the case with the Palais des Beaux-Arts in Brussels. Here, the investment has been more substantial. It is certainly worth it, as this is one of the finest castles in Wallonia.”
The studies were carried out in close and seamless collaboration with the Provincial Buildings Department, the Walloon Heritage Agency, the Royal Commission for Monuments, Sites and Excavations, and the health and safety coordinator. TPF Engineering’s assignment was organised as follows: assessments of the castle’s overall stability; prioritisation and budget estimates based on studies for both preventive conservation and restoration; preparation of tender and construction documents in line with the budgets available; and, finally, support for the works management team during construction.

Jean-Michel Frenay explains: “A distinction must be made between direct preventive conservation measures, essential to address the most serious defects, such as cracks in the façades and problems with the roofs, and to prevent collapses or further deterioration, such as water ingress; and measures for the building’s future use, such as bringing a majestic wooden staircase up to code and building two metal staircases.”

One surprise can hide another
The 19th- and 20th-century interventions were generally of poor quality, and many defects had been concealed. Jean-Michel Frenay explains: “Necessarily, the initial condition survey continued throughout the works, as one surprise gave way to another. We even came across double walls. Provincial staff were on site at all times, including someone who carried out surveys as elements were dismantled. We were there during the works to provide technical support.” The roof timber was often rotten where it was embedded in the masonry supporting it. The castle was built in a wet area and is also surrounded by imposing moats. In such conditions, even oak eventually rots if exposed to changes in humidity.

Reinforce like for like wherever possible
Where reinforcing an element required its replacement, the work was carried out “using traditional methods”, with glass-fibre-reinforced resin, for example, used only in localised, concealed areas. The methodology followed since the Venice Charter, known as critical restoration, means that the work is far more respectful of the heritage than in the past. The aim is to preserve as much of the existing fabric as possible and make the building’s history visible through the centuries. However, these restoration requirements must also be balanced with sustainability principles and safety standards. New floors were therefore built using glued laminated timber and OSB panels, to meet current load requirements and span large distances. Original materials were retained wherever possible, limiting the use of new stone, for example.
Jean-Michel Frenay says: “Let’s be clear. Restoration does not mean turning back the clock. In many respects, the castle is now performing better than it ever has.”
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeRenovating existing buildings
- SubjectProjects


















