A timeless construction site, a truly human adventure

Texte Philippe Selke Photos Ets. Moury (drone) et Province de Liège Dép. Comm. (autres)

Tout a été manutentionné avec la grue via les échafaudages de façade, pour amener à l’intérieur les nouveaux matériaux et évacuer les gravats de démolition. (photo : Province de Liège)
Tout a été manutentionné avec la grue via les échafaudages de façade, pour amener à l’intérieur les nouveaux matériaux et évacuer les gravats de démolition. (photo : Province de Liège)

The comprehensive restoration of a listed 16th-century château is almost like stepping back into the builders’ era: virtually everything is done by hand, with precise craftsmanship to recover its original appearance. This is the human adventure that Entreprises G. Moury, GM, its partner company Lixon and their specialist subcontractors have been part of for more than 7 years, finally freeing the majestic building from its scaffolding. Denis Collin, site manager at GM, tells us about some of the distinctive features of this exceptional project.

Located in Amay, Château de Jehay, owned by the Province of Liège, is one of the finest in Wallonia.

Entreprises G. Moury: GM, which has extensive experience of major construction projects and holds D24 accreditation, was responsible for structural consolidation and restoration of the exterior envelope. Before work began, a preparatory phase involved draining part of the moat to build a slab on micropiles. This enabled the Province of Liège to erect perimeter scaffolding, which served as an essential hub throughout the works.

The ravages of time laid bare

Denis Collin explains: « We began by removing the floors and suspended ceilings to expose the structure and check the condition of the oak beams, as well as the cross-section of those that needed replacing. The oldest date back to the château’s origins, so they have been in place for nearly 500 years… We left removing the roof until as late as possible to keep the rain out and work in reasonably dry conditions. While some teams cleared the interior, others worked on restoring the façades: cleaning, preliminary sandblasting and replacing all damaged elements, including around 700 ashlar stone components. » The masonry work and some formwork were carried out by GM’s own workforce, while the contractor brought in specialist craftspeople, including Henri Lefin for the restoration of the roof structure, floors and roofing, and Marc Ledent for the façade restoration. Stone masons (Neo-Lith) spent 5 years working blocks quarried at Vinalmont to create unique pieces, which were fitted on site to slot into a precise location on the façade. “

A preparatory phase involved draining part of the moat to build a slab on micropiles to support perimeter scaffolding. (photo: Province of Liège)

An incalculable amount of elbow grease

The length of the project reflects the scale of the task, as well as the organisational and handling challenges involved in this type of restoration. GM was not initially due to work on the interior walls, but it and Lixon secured two additional contracts covering this work, bringing greater coherence between the exterior and interior, particularly in terms of stability around the beam supports. Denis Collin explains: « This made the project easier to organise, as we could work on all the different sections in parallel, phase by phase: the main wing, which is the oldest, then the central section and finally the keep wing. We worked inside while beginning to cover the exterior. »

A tower crane installed in the château courtyard could reach all the access tracks in the moat. Everything was moved by crane via the façade scaffolding, bringing new materials inside and removing demolition rubble. « For example, restoring a single interior wall required 14 m3 of new masonry. All the rubble had to be taken out in buckets through the windows and then down the scaffolding, as the floors could not take any load! » Everything that could be reused and was in good condition, mainly bricks, including old ones, was reused.

Apart from the tower crane and a few small power tools, the work was done with sheer elbow grease, just as in the days of the cathedrals. Denis Collin explains: « Everything was done by hand, the traditional way, on site, whether it was stone cutting or masonry restoration. Working with lime demands an almost timeless pace: mixing it yourself, little by little, dividing the work into lots of small areas, and doing a huge amount of handling, with almost two labourers for every mason. And below 5 degrees, it is impossible to lay lime masonry, which further extends the project. Our workers were obviously not used to working this way. But what unsettled them most was having to build to match the existing structure, which was sometimes out of plumb and not level! » 

« We began by removing the floors and suspended ceilings to expose the structure and check the condition of the beams. » (photo: Province of Liège)
Stone masons worked the blocks into unique pieces, fitted on site to slot into a precise location on the façade.

When Notre-Dame enters the picture

The replacement of the window frames was a separate contract, awarded jointly with Mosabois, the joinery company within the Moury-Construct group. It had to source 35 m3 of oak just for the frames, at a time when prices were soaring… and the finest pieces were reserved for rebuilding the roof structure of Notre-Dame in Paris! As a result, some of the sections needed for the frames were delayed by 6 months. One of the project’s defining moments was the removal and reinstatement of the two spires on the château’s towers, after asbestos removal using a mobile elevating work platform and restoration at ground level. Exterior works are still under way and are due to be completed in spring: restoration of the domain’s gatehouse tower, separated from the château by a moat and, fortunately, more accessible than the château itself.

Denis Collin concludes: « Personally, I will remember this exceptional project as a superb experience and a wonderful human adventure, working for a client that demanded quality at every level. My sole point of contact was the Province of Liège, which combined the roles of client, design team and site supervisor. » Just like in the days of the cathedrals…

One of the project’s defining moments was the removal and reinstatement of the two spires on the château’s towers, after asbestos removal using a mobile elevating work platform and restoration at ground level. (photo: Province of Liège)

The project in figures

  • Removal and rebuilding of brick and rubble-stone masonry walls: 319 m³
  • Removal and rebuilding of facing masonry: 32,25 m³
  • Work on Vinalmont limestone ashlar: +/-700 pieces (replacements, stone inserts and pinning)
  • Timber supplied (floors, roof structure and window frames): 182 m³
  • Repair and strengthening of timber roof structure with resin: 11965 dm³
  • Removal and reinstatement of timber floor structure: 1400 m²
  • Natural slate roofing: 1430 m²

Question about this story? Ask your question

Who worked on it

  1. ClientProvince de Liège (chantier subventionné par l’Agence wallonne du Patrimoine: AWAP)
  2. ArchitectProvince de Liège
  3. Main contractorLes Entreprises G. Moury: GM, en association avec Lixon

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeRenovating existing buildings
  • SubjectProjects
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.