Projects

A refurbishment that lives up to the designers’ ambitions

Texte Philippe Selke Photos Franki

« Nous avons beaucoup démoli, ne gardant que la structure portante, que l’on a ensuite modifiée et renforcée à certains endroits. »
« Nous avons beaucoup démoli, ne gardant que la structure portante, que l’on a ensuite modifiée et renforcée à certains endroits. »

In Liège, the modernist thermoelectric power station is the penultimate building to be refurbished on the Val Benoit site. Delivered by main contractor Franki, this major project is transforming an iconic industrial building into contemporary offices for the Cité des Métiers, FOREM and ULiège. Preserving the original concrete structure and using high-quality materials help give the building a unique aesthetic while preserving its history.

,Designed in 1932 by architect Albert-Charles Duesberg and engineer Fernand Campus, the thermoelectric power station comprises several rectangular buildings that housed the central heating plant for the Val Benoit site and a thermodynamics laboratory. The tower, which housed a giant pressure gauge and a water tank, is a landmark visible from all around. Its tall glazed façades create highly attractive interior spaces.

The main contractor is currently giving the tower, an essential heritage feature and the site’s “beacon”, a facelift. It had a large crack.

Assessing the building

Julien Belligoi is a Project Manager at Franki. He has followed the project closely since March 2022: “We were faced with a group of buildings with a highly unusual layout, in the condition they were in, with only asbestos removal having been carried out beforehand. We demolished a great deal, retaining only the load-bearing structure, which we then modified and strengthened in certain areas. Cutting openings, installing new floor slabs, reinforcing the structure with steelwork… all this was done by our own teams. Provisional acceptance of the Cité des Métiers section took place last April, and we are now addressing the final snagging items. Meanwhile, work is still under way on the shell-and-core section for FOREM. This second phase will be completed in the summer.”

As the masterplan called for the site’s history to remain as visible as possible, many sections of façade were rebuilt like for like. Deconstruction was therefore carried out with the aim of salvaging materials for reuse on site, including bricks, rubble stone and sills… 

The height of the interior spaces is impressive.

Key construction challenges

The contract was divided into separate lots. Franki was responsible for the structural work, finishing and overall coordination. Julien Belligoi explains: “Coordinating companies that are joint contractors rather than subcontractors is not always straightforward. It was a first for me. The joint contractors selected by the client were no newcomers, so discussions were extensive… and energy-intensive.”

A second challenge stemmed from the successive crises we have experienced: COVID, the war in Ukraine, soaring energy prices… “The result was a sharp rise in costs, as well as supply difficulties, for example with the profiles for the external joinery and the fan coil units. Where the normal lead time was 10 weeks, we sometimes had to wait 30 to 35 weeks.”

Finally, working for three different building users posed an additional challenge. Franki showed flexibility in dealing with requests for changes during the construction work.

Almost a century old, the original concrete, cast against rough-sawn boards, has been repaired locally, sandblasted and left exposed as a trace of the past.

Ambitions reaching new heights

Almost a century old, the original concrete, cast against rough-sawn boards to imprint a pattern, was simply sandblasted and left exposed as a trace of the past. The height of the interior spaces is impressive. Finishing work, mostly subcontracted, required the use of scaffolding up to 15 m high. Numerous acoustic panels were installed to reduce reverberation. Ash interior joinery, aluminium frames… the materials used are high quality and built to last. As lifting equipment could not be used, many elements had to be positioned by hand using lifting beams.

As we go to press, the main contractor is giving the tower, an essential heritage feature and the “beacon” of the entire site, a facelift. It had a large crack. Julien Belligoi says: “We are removing sills, rebuilding brick façades… all at a height of 50 metres. I’m very proud of what we are delivering, and I don’t think I’m alone. We have managed to come close to the architects’ exceptionally high standards.” 

Question about this story? Ask your question

Who worked on it

  1. ClientSPI
  2. ArchitectAM Baumans-Deffet Architecture et Urbanisme: Architecture Alain Dirix (A.A.D.): Lemaire Ingénieurs.
  3. Main contractorFranki

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeRenovating existing buildings
  • SubjectProjects
Share this article

Advertisement

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.