Projects

A cantilevered façade, the landmark feature of a mixed-use development opposite Liège-Guillemins station

A cantilevered façade, the landmark feature of a mixed-use development opposite Liège-Guillemins station

The Guillemins district in Liège is (once again) taking shape. Ideally located opposite the station, a few hundred metres from the future Paradis Express complex, the Ardent Group’s Office Centre was completed in under 3 years. This property development, which is aiming for Breeam Very Good certification, is distinguished by a cantilevered glazed façade that called for considerable architectural and technical ingenuity.

The four brand-new buildings at the Office Centre will primarily accommodate offices and coworking spaces, as well as a few shops, 12 flats and a 102-room hotel.

lumiares-kopieren

Some of the windows in the main building are fitted with lights whose colour and intensity will vary according to the level of natural light outside.

Different levels of fit-out

François Cormeau, project manager at Franki (Willemen Group), led the team of project managers and site managers and monitored the work on a day-to-day basis.
“Our company was awarded the overall construction contract. We therefore built the retail units (without fit-out), the office floorplates (unfitted), the hotel (equipped and furnished), the flats (some of which will be customised by the client) and two fully equipped parking levels.” While 3 of the 4 buildings are limited to 6 storeys, the fourth rises to 10 levels (9 floors plus the roof), making it the tallest building in the area.

20181203_115526-kopieren

The original system used for the cantilever is often used to construct floor slabs in the petrochemical sector, to prevent cracking in large tanks and ensure they are perfectly watertight.

The challenge of the foundations

Did the project present any particular challenges?

“First of all, the foundations,” explains François Cormeau. “The entire project site is built up, which meant that, given the site’s location, the bus route and traffic in the neighbourhood, removing the excavated soil and building the basements were no easy task.” This was all the more challenging given that a wall of 530 secant piles had to be installed around the site perimeter, along with 450 piles to support the loads from the buildings within the site. François Cormeau adds: “We were also below the water table when we built parking level -2. We therefore had to create a barrier of watertight piles to keep the water out and, using a pumping system, we were able to build the bottom slab and make the car park watertight.”

img_6095-kopieren

The 102-room hotel, originally planned to face the street, was ultimately built
within the site.

The challenge of the cantilevered glazed tower

Another challenge was the 10-storey building, which cantilevers from the 2nd floor upwards. “The forces and load transfers are therefore highly unusual,” says François Cormeau. “The cantilever was originally supported by a steel structure on levels +2 and +3. These levels would therefore have needed a heavy structure to counterbalance the cantilever. Working with the Italian engineering consultancy Medipav, we proposed removing this structure and replacing the load-bearing system with lightweight, cantilevered post-tensioned slabs, a system that was entirely new in Belgium. Instead of a conventional steel structure, steel strands are laid out on formwork.

The concrete is then poured, and the cables are subsequently tensioned to give them a certain rigidity. The cantilever is therefore no longer supported solely by the structure below, but by each of the slabs that make up the building. This also frees up space on the two lower levels.”

The curtain wall on this tower also had to be combined with the cantilever without risking cracking. Depending on the loads in the building and the long-term creep of the concrete, the tower needs to be able to move, and the curtain-wall glazing must be able to accommodate these movements.

François Cormeau concludes: “The architectural design is a real success. The buildings are attractive and do not feel oppressive despite their imposing appearance. And the client is very pleased with the result.”   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeFaçades and building comfort
  • SubjectProjects
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.