From 2022, the outdated prisons in Saint-Gilles, Forest and Berkendael will be replaced by a brand-new prison complex in Haren. The “village” will comprise around ten buildings housing smaller units, improving the quality of life for inmates. In just 6 months, De Waal Solid Foundations installed no fewer than 4,000 double-displacement screw piles, without vibration.
Originally a department of its Dutch parent company De Waalpaal, De Waal Solid Foundations has since built up more than 60 years of experience in installing foundation and retaining piles. The company is best known in the sector for its double-displacement screw piles: since developing its own system 30 years ago, along with a dedicated fleet of machinery, GVS piles have become virtually the company’s trademark. “We also offer other solutions, of course, but we have chosen to specialise in a limited number of techniques. This allows us to stay focused, make fewer mistakes and become specialists in deep foundation work,” says Olivier Rens, managing director of De Waal.

Installation of GVS piles on a site in Kallo. Thanks to its extensive fleet of machinery, De Waal Solid Foundations can easily take on major projects.
10 buildings, 4,000 piles
At the start of this year, De Waal Solid Foundations was one of the first construction companies to set foot on the site of the new prison in Haren. The former site of the now-bankrupt boiler manufacturer Wanson covers around 15 hectares and will accommodate 1,190 inmates in a few years’ time. Olivier Rens says: “This is a very interesting project for us, because this is no ordinary prison. The prison village consists of around ten buildings set at different levels. The site is sloping, with a difference of almost 8 metres between its highest and lowest points. After a detailed ground investigation, we calculated the appropriate pile lengths based on the survey results. In the end, we installed 4,000 GVS piles ranging from 8 to 22 metres in length. It was no easy task, but one we can be proud of.”
Always ready to respond
“In our sector, we tend to take things one day at a time,” says Olivier Rens. “We often don’t know what will happen beyond the next few weeks. Given that GVS piles are the best solution for 99% of construction projects on the Belgian market, it’s clear that we need to be able to respond quickly.” With sufficient staff at its disposal, De Waal Solid Foundations can react promptly to new requests. Good organisation is crucial here: “We can send 30 teams out across Belgium every day, or around 100 people. A structured schedule is obviously essential if we are to be flexible for our clients.”

At the prison village site in Haren, De Waal Solid Foundations installed 4,000 GVS piles ranging from 8 to 22 metres in length.
De Waal, a multinational
The De Waal Group, with De Waal Solid Foundations as its cornerstone, can be described as a true multinational: in addition to De Waal Solid Foundations and the Sondex consultancy, the group also owns two subsidiaries operating in Eastern Europe. “We consider this a significant market. With the skills and experience we have built up over recent decades in our own region, we can outcompete rivals in countries such as Poland and Romania. We also want to continue growing in Belgium, the Netherlands, Luxembourg and France. We have built a strong reputation there: it is well known that we deliver quality, do not charge extra for every little thing and take responsibility. Our roots are here.”