200 tonnes of steel to connect Charleroi Airport by rail

Fleurus station, close to Brussels South Charleroi Airport, has been completely renovated to make it easier to reach the airport by public transport. The railway, combined with TEC shuttle buses, now benefits from new steel infrastructure, including an impressive footbridge over the tracks. This demanding project for SNCB was completed without a hitch by ARTES, a company well versed in this type of work.

Renovating and upgrading railway infrastructure is a major priority for the future of mobility in our country. From Milmort, Maubray and Jurbise to Franière, ARTES has lost count of the projects it has completed, installing steel structures over railway tracks. Such work must be meticulously planned in advance to fit within the short track closures scheduled by Infrabel. Benoît Kaisin, project manager at ARTES: “Infrabel schedules track closures up to 2 years in advance. Our first priority was therefore to organise the work so that we could take advantage of the weekend closures planned for June 2021.”
Project management on track
At the start of the project, ARTES’ design office first carried out the structural design of the footbridge, which is 36 m long and 13 m high. Supported by 6 steel columns filled with concrete, the structure comprises an outer frame made of steel tubes, within which a second, glazed volume is inserted to protect passengers from the weather. A walkway with stainless steel fabric cladding is provided for window cleaning and maintenance.

The construction work itself began in November 2020. The aim was to complete as much work as possible away from the tracks beforehand, so that the short periods of traffic closure could be used to the full. Benoit Kaisin: “We therefore pre-assembled the footbridge structure on the ground, away from the tracks. The footbridge’s steel deck was also installed in advance, as it would have been very difficult to fit it above the tracks. The metal fabric cladding was installed at the same time, as it was essential to ensure the safety of the workers during the subsequent operations.”
The big moment came at night over the weekend of 5 and 6 June 2021. A 700-tonne crane lifted the footbridge into position. Everything went perfectly. Over the following weeks and months, the stairwells clad in expanded metal were installed, along with the steel frames for the lifts, finished in embossed aluminium to striking effect.

A highly efficient project
Although the steel footbridge over the tracks was the project’s centrepiece, it represented only part of the work. To the south of the tracks, a station building comprising a waiting room, an automated toilet and a technical room on the first floor shares the footbridge’s all-steel construction method. To the north, a canopy with an adjoining cycle shelter provides a place to wait for the airport shuttle. The scheme also includes a large car park with 150 spaces, a 30-space car park along Avenue de la gare and a stormwater basin beneath the access road to the roundabout leading to the main car park. In addition to steelwork contractor Van Eycken, several subcontractors contributed to the successful delivery of the project, under ARTES’ expert coordination.
The use of galvanised steel, painted in the workshop and assembled entirely with bolted connections, gives the whole scheme a distinctly modern appearance, but above all ensured an efficient project, as desired by the client. ARTES expects to complete its part of the work by the construction industry holiday period. The lifts, which are outside ARTES’ contract, will then be installed, and the various technical systems commissioned, so that SNCB can officially open the new station during September.
Question about this story? Ask your question
Who worked on it
- ClientSNCB
- ArchitectSNCB
- Main contractorARTES
Keep following this
Get an email when a new story is published. No account needed.
- ThemeTransforming infrastructure and territories
- SubjectProjects


















