All traffic switched onto the lanes towards Marche-en-Famenne

All traffic switched onto the lanes towards Marche-en-Famenne

A new stage in the N4 rehabilitation and safety upgrade works in Tenneville: from Thursday 22 October, all traffic at the works will be switched onto the lanes towards Marche-en-Famenne.

As at the start of the works, traffic will continue to use one lane in each direction throughout the entire area, with the speed limit set at 50 km/h.

Road users will use the outer part of the road, as the central section and its island still need to be completed. Traffic will run on the new sub-base of the N4. The surface course will be laid later, once the entire road has been completed.

The traffic signs and road markings for the switch will be installed during the night from Wednesday 21 to Thursday 22 October.

The central sewer, located beneath the future central island of the N4, has now been installed. Work has focused on the outer lanes, which usually carry traffic towards Marche-en-Famenne. The island in the central section still needs to be completed. Work will now focus on the lanes that usually carry traffic towards Bastogne, and on constructing the central island.

At the end of the works, a final layer of surfacing will be laid across the full width of the road in both directions.

During these operations, which are expected to take place around May 2021, traffic in one direction will be fully diverted for six nights. Both directions will remain open during the day.

The works are expected to be completed by the end of the first half of 2021.

REMINDER

Temporary safety measures for the route through Tenneville were introduced several years ago, reducing traffic to one lane and the speed limit to 70 km/h. These measures helped reduce the number of fatal accidents on this stretch.

This project, which began on 31 March 2019, will make these measures permanent, helping to ensure the safety of road users and local residents, for whom this road remains a dangerous area.

The works involve:

Rehabilitating the road surface through Tenneville over a distance of approximately 4 kilometres ;

Replacing the temporary road-narrowing measures with a more substantial central island , marking out one lane of traffic in each direction. The island will be traversable at several points to allow people to cross from one side of the road to the other;

Rehabilitating the sewer network and reviewing the surface water drainage system.

Traffic measures and impact on traffic

Throughout the works, heavy goods vehicles weighing more than 3.5 tonnes are strongly advised to use the diversion from Barrière de Champlon to Barrière Hinck via the N89, N848 and N826.

Heavy goods vehicles making long-distance journeys are advised to use the E411/A4 and E25/A26.

Shops will remain accessible throughout the works, and residents will, of course, continue to have access to their homes. They will be given timely notice of the few days of asphalt laying when they will be unable to use the road.

The works have a budget of more than 12 120 000 € excluding VAT , funded by:

SOFICO (approximately 10.000.000 € excluding VAT);

The Municipality of Tenneville, which is contributing to the funding of the surface water drainage works and improvements to the roadside areas, and will also install new drinking water pipes at a cost of nearly 1.000.000 € excluding VAT;

SPGE, which is funding the rehabilitation of the sewer network and the construction of new connections, at a cost of more than 992.000 € excluding VAT;

OTW, which will build eight bus stop areas at a cost of more than 185.500 € excluding VAT.

The works are being carried out in collaboration with SOFICO’s technical partner, SPW Mobilité et Infrastructures.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeRenovating existing buildings
  • SubjectNews
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.