On the railway line between Brussels and Quévy, ARTES recently replaced the deck and bearing beams of an overbridge in Jurbise. The original metal bridge, dating from 1894, was replaced with a concrete structure. The most spectacular stage was installing the structure in a single night, but the preparatory work is also worth a closer look, as it was key to the operation’s success. Simon Goffin is a site manager for ARTES. Used to working on building projects, he carried out his first railway infrastructure project in Jurbise. He takes us through the project.

The existing structure comprised a steel frame with concrete-encased cross-bracing, which formed the bridge deck. Approximately 25 m long, it carried a single carriageway with pavements on either side, crossing the 4 railway tracks leading from Jurbise station towards Mons. ARTES was tasked with demolishing it and replacing it with a new bridge made of reinforced concrete, with 2 welded plate girders in the side walls, while strictly adhering to the traffic closures scheduled by Infrabel.

Prefabrication in the work area
While the existing bridge was being demolished, work began on prefabricating the new bridge and bearing beams in the field next to it. Simon Goffin explains: “The deck slab had to be built with an upward camber. We therefore made a lean-concrete working slab incorporating this camber, which allowed us to form and pour the deck slab directly to the required profile. Before we could fix the reinforcement and pour our slab, we first had to install the welded plate girders in each of the side walls. To ensure the girders were at the right level in the structure, we installed gantries with hoists so that the steel beams could be suspended using lifting lugs. We were then able to fix the reinforcement and pour the slab, before building the side walls. Once the formwork had been removed, the walls had an attractive textured finish, achieved using formwork liners attached to the formwork. New bearing beams were also made in the prefabrication area, before being installed on either side of the tracks.

Building an access track for the lifting crane
Partly across the field and partly on the road, a track with sufficient bearing capacity had to be built to accommodate a 650-tonne crane with a 50-metre boom. The crane needed to be able to lift the bridge, which weighed nearly 250 tonnes, and then move it about 30 metres to its final position. It took almost a week to assemble the crane, whose components were delivered by dozens of lorries. This was no easy task, given how narrow the local roads are. Simon Goffin explains: “Two days before the big day, we carried out a lifting test to anticipate and avoid any last-minute problems.”

Installation overnight
The big moment came during the night of 15 to 16 January 2022, taking advantage of the closure scheduled well in advance for this purpose. Everything went perfectly, with the bridge lifted and installed in just a few hours. The structure was set on jacks while the supports were formed and sealed a few days later. In the following weeks, work turned to the finishing touches: installing expansion joints, kerbs, asphalt, guardrails and overhead line protection, enabling ARTES to hand over a turnkey bridge at the end of February. At the same time, the areas used for the work site and crane track were restored.

Anticipating problems
ARTES carried out the work under this contract itself, although it subcontracted a few specialist tasks, such as demolition and handling. A team of 4 workers carried out all the work throughout the project. Simon Goffin says the project involved a great deal of coordination and planning ahead to ensure everything went as expected on the big day. And that is exactly what happened in Jurbise! A rewarding first project, then, for the site manager.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeTransforming infrastructure and territories
- SubjectRailway works