Liège’s BUSWAY gets on track

Texte Philippe Selke Photos dbcreation (Anthony Dehez)

Il sera désormais toujours plus rapide de rejoindre le centre de Liège en transport en commun qu’en voiture aux heures de pointe. Tout cela à bord de tout nouveaux bus articulés 100% électriques.
Il sera désormais toujours plus rapide de rejoindre le centre de Liège en transport en commun qu’en voiture aux heures de pointe. Tout cela à bord de tout nouveaux bus articulés 100% électriques.

In December 2024, we introduced you to the construction site for the high-level service bus, known as the BUSWAY, whose first operational line connects Guillemins railway station to Sart Tilman. This major project, carried out by Nelles and TRBA, is now complete, and the BUSWAY is up and running, much to the delight of passengers and local residents. We take stock with Tony Robert, Project Manager at OTW, and Thomas Bastin, site manager at Nelles.

Tony Robert can be considered the “driving force” behind the BUSWAY, having worked on it for years with great dedication and passion. Shortly after the B2 line was inaugurated, he reflected on the work completed: “It is a real pleasure to see this project come to fruition and to be able to offer passengers a 2.0 mobility experience. We are already seeing good use of the cycle paths built alongside the traffic lanes.  

The BUSWAY stops stand out for features reminiscent of the Tram: light granite kerbs, illuminated columns, totems, CCTV cameras…

Thanks to dedicated funding from SPW, these paths now provide a fast and safe way to reach the Parc Scientifique or Sart Tilman. But our greatest source of pride is having brought together the skills and energy needed to ensure that Wallonia’s first BUSWAY line meets its ambitious objectives: reliability, speed and frequency that will make public transport the quickest way to reach the centre of Liège during rush hour. All aboard brand-new 100% electric articulated buses. It is worth noting that this B2 line runs, like the tram, from 5 am to 1 am. We were also able to rely on the expertise and responsiveness of the NELLES Frères, TRBA consortium to complete all the infrastructure works with as little impact as possible on local residents and mobility.”

Managing construction challenges and residents’ concerns

Thomas Bastin: “Additional work, such as the complete reconstruction of the road structure, and unforeseen site challenges meant we could not meet the original 300-calendar-day deadline. We were granted a 6-month extension, which put residents’ patience to the test, and did everything we could to finish by the end of June. We then used August to address the few issues raised during the acceptance inspections and install various items of equipment, so that everything would be ready for the inauguration on 15 September.”

The specifications included keeping traffic moving in both directions throughout the works, a requirement on which the City of Liège was adamant. However, the road was not wide enough to allow this in some places. Fortunately, arrangements were made, with both companies adapting their resources and methods, including night work and shifts running from 6 am to 23 hours. Tony Robert played an active role in successfully securing the City’s approval for these proposals.

​Cycle paths built alongside the traffic lanes now provide a fast and safe way to reach the Parc Scientifique or Sart Tilman, thanks to dedicated funding from SPW.

Thomas Bastin: “Working in constant consultation with OTW, we were able to maintain an average of 40 workers on site at all times, moving them from one area to another across this large project so that we could work on all fronts simultaneously. Everyone showed flexibility, and that is what enabled us to finish on time.”

OTW supported local residents by setting up an 0800 number and an email inbox where they could send in their questions and concerns. This system could usefully be repeated on future projects. Nelles also showed its responsiveness here, resolving occasional problems with access to properties, among other things.

August was used to address the few issues raised during the acceptance inspections and install various items of equipment, so that everything would be ready for the inauguration on 15 September.

Safe travels to passengers on the B2!

The BUSWAY stops stand out for features reminiscent of the Tram: light granite kerbs, illuminated columns, totems, CCTV cameras… and all the cables that power this equipment. Nelles added these finishing touches in time for the inauguration.

Thomas Bastin highlights the excellent spirit that prevailed throughout the project, with all parties working towards the same goal: making the first BUSWAY line a success and encouraging the public to make full use of this “almost-tram”: “Whether working with Tony Robert or with the TEC inspectors who followed the project, the collaboration was very enjoyable. And it is always a pleasure to receive congratulations from all sides, including local residents, as happened at the inauguration!”  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeTransforming infrastructure and territories
  • SubjectInfrastructure
Share this article

Advertisement

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.