A warm welcome for patients and their families is essential for a hospital. Of course, this also means having enough parking spaces. But what happens when an underground car park is at risk of flooding? Deschacht, Galère and Lucas David came up with a tailor-made solution.

The two levels of the original car park at the Centre hospitalier régional de Namur are being extended to better meet patients’ needs. The new garage will cover 8,000 m² per level, with more than 1,000 spaces: a 50% increase. Work began in November 2022 and is being carried out in two phases, the first of which was completed on 2 October. Why two phases? Because part of the car park has to remain accessible to patients, staff and families.

For this major project, parking operator Effia called on contractor Galère, which entrusted the earthworks and drainage to Lucas David. “First, we had to demolish the original car park, which had a steel frame, and rebuild it with an additional level,” explains Matthew Leroy of Lucas David. “We handled the earthworks and drainage, using products from Collinet-Deschacht.”

“Polyethylene products require a specific approach and technical expertise that not everyone has, but Deschacht handled their installation perfectly.”

Unexpected challenges

Galère commissioned a design office to establish the required criteria. As the car park is in constant use, it has to meet stringent standards. However, the main challenge on site proved to be water management: “We had to excavate to a depth of 4.9 m, but we encountered the water table at just 1.6 m,” says Matthew Leroy. “We were constantly working below the water level and had to find a rapid, long-term technical solution to prevent the garage from flooding during storms.”

“When we consulted the design office, it suggested a fairly straightforward solution: install two pumps, so that one would always keep running if the other failed,” explains Laurent Demaret, project manager at Galère. “This meant installing a larger inspection chamber than initially planned, particularly as the pumps needed to be far enough apart to prevent a vortex effect. We therefore opted for a 1.8 m diameter inspection chamber, custom-made by Collinet.”

Oil separator and pumping station

Deschacht supplied not only an HDPE sewer network with diameters ranging from 110 to 400 and around ten custom-made polyethylene inspection chambers, but also an HDPE oil separator and a double-wall HDPE pumping station in unusual dimensions.

“Thanks to Deschacht’s design team, the expertise of our partner Ecosolutions and the know-how of Collinet, our production workshop, we were able to meet the challenge,” explains Dimitri Steilen, project manager at Deschacht. “We had to find a technical solution to the project’s challenges, including the water table and the very tight delivery schedule. We also had to meet the design office’s requirements for material quality and safety standards.”

“An HDPE oil separator was needed to treat the car park’s wastewater before it was discharged into the sewer network. The water now passes through a pumping station, which also handles all the rainwater. To achieve this, we used a Ø1800 double-wall HDPE tank, 5 m high, with a 4 m³ sump and an HDPE ladder, a system fitted with fall-protection grates and two Grundfos pumps, each with a capacity of 30 l/s.”

To prevent groundwater pressure from pushing the various components upwards, Lucas David installed concrete slabs, together with an anchoring system and a stainless-steel ring.

To prevent groundwater pressure from pushing the various components upwards, concrete slabs were installed, together with an anchoring system and a stainless-steel ring.

Polyethylene, an ideal material

Both key components are made of polyethylene, an ideal material for this type of project. “Polyethylene has the advantage of allowing products to be made to measure, even on a huge scale,” explains Dimitri Steilen. “It is also 100% watertight and can be installed more quickly than concrete, for example. That was particularly useful on this project, where we had to pump out groundwater continuously.”

The oil separator is also fitted with an alarm that alerts the client when the oil layer has reached its maximum level and the separator needs to be emptied. The pumping station’s tank is fitted with a level sensor and a control cabinet that enables the pumps to be monitored continuously. Ecosolutions also offers an annual maintenance and servicing package.

The main challenge on site proved to be water management.

A reliable partner 

When it came to choosing a supplier, Lucas David naturally turned to Collinet-Deschacht. “We’ve been working together for nearly 10 years and we trust each other,” explains Matthew Leroy. “We have an excellent working relationship, and the sales team responds quickly whenever plans change. We saw this first-hand on this particularly complex project. Polyethylene products require a specific approach and technical expertise that not everyone has, but Deschacht is highly skilled at installing them. We’ve also already attended training courses at Deschacht to improve our installation of polyethylene pipes.”  

Een zakelijke vraag aan DESCHACHT Plastics? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectNews
  • CompanyDESCHACHT Plastics
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.