Widening the Scheldt | Tournai

Tournai was founded and prospered along the Scheldt. The city is currently seeing the areas along its river completely renovated. The quays that have yet to be redeveloped, from Pont Devallée in the south-east to Pont Delwart in the north-west, will also be revamped. The Scheldt will also be widened over 250 metres alongside Quai Saint-Brice and beneath Pont des Trous, to allow Va-class barges (2,000 tonnes) to pass. We asked Christophe Vanmuysen, Inspector General at SPW and the official in charge of the project, to bring us up to date on the work under way and planned.
In Tournai, the Scheldt is no placid river

Quai Saint-Brice as it will look after being narrowed.
This project, costing almost €37 million and co-funded by the European Union (40%) and Wallonia (60%), is part of the European “Seine-Scheldt” project. This includes infrastructure works along the entire link between the two river basins. Christophe Vanmuysen: “The Tournai project has often been linked to the Seine-Nord Canal on the French side. This new canal was due to be completed in 2020, but the French authorities requested an extension of the validity of the European funding until 2022 and are also expected to submit the project to the new European investment programme for 2021-2027. In any case, regardless of the additional traffic that the Seine-Nord Canal could bring, the Scheldt in Picardy Wallonia deserved a modernisation effort. Because of the bottleneck at Tournai, a standardised 2,000-tonne barge (class Va) cannot pass through today. And a standardised 1,350-tonne barge (class IV) only just fits between the arches of Pont des Trous. River traffic through the city centre is disrupted when the flow reaches a certain level, so widening the river is also about making it possible to navigate safely more often.”

The new Pont-à-Ponts, as it looked in 2019.
Always going back to the drawing board
The replacement of the central section of Pont des Trous is an iconic phase of the widening project. The people of Tournai are very attached to this example of medieval military architecture (13th century), which is not actually a bridge but a remnant of the city’s third defensive wall. SPW, which owns the bridge and the waterway and is the client for the project, left the choice of architectural design in the hands of the people of Tournai. Since the first design, featuring a metal lattice, was rejected by the public in 2005, a public consultation and participatory workshops have followed one after another. Christophe Vanmuysen: “The participatory workshops produced a design featuring three slender, openwork stone arches, with no walkway. The Tournai municipal council unanimously submitted this design to the minister so that it could be included in a permit application in November 2017. The application is still under review.” Opponents of the project are not giving up, however. The latest initiative has led to ICOMOS requesting a moratorium to prevent damage to the UNESCO listing of the Belfry and the Cathedral…

The new Pont-à-Ponts being installed on 9 June 2018. (Photo: Didier Dominicus)
A project in 4 phases
Or rather, 3 for now, as phase 4, covering Pont des Trous and its surroundings, has not yet received planning permission. The other 3 phases are under way. The most spectacular is probably phase 1, which involves widening the Scheldt alongside Quai Saint-Brice and replacing Pont-à-Ponts with a new steel structure. Started in April 2017, it is due to be completed by summer 2019. Narrowing Quai Saint-Brice involves substantial civil engineering work: drilling and concreting 219 concrete piles to create the new quay profile using a secant pile wall, 15 to 16 metres deep and 1.30 m in diameter… The new Pont-à-Ponts was installed early in June this year and opened to traffic in September. However, finishing work still needs to be completed, including laying the final surfacing, as the new bridge has not yet been tensioned.
Phases 2 and 3 are under way. They involve refurbishing 2.7 kilometres of quays out of the 4 kilometres within the city walls. Christophe Vanmuysen: “The work to widen the Scheldt also includes urban improvements in areas affected by the widening works. A significant proportion of the project’s €37 million budget is therefore being spent on improving the urban environment, for the benefit of the people of Tournai and tourists.”
This mega-project by Tournai standards is being carried out by the Galère-Wanty joint venture, which is bringing in subcontractors for some of the more technical work. The bridge was built by Techno Métal Industrie in Namur (Andenne). The design office is Greisch and the inspection body is Seco.
Most recently, Gore quarry in Andenne, owned by SPW, was selected to cut the stone for the future Pont des Trous.
This project, which is essential to the development of waterborne transport, showcases Walloon expertise.