Wallonia’s motorways and main national roads: projects for the return to work

As the summer holidays draw to a close and many road users prepare to head back to school or work, SOFICO is taking stock of the main works they may encounter on Wallonia’s motorways and strategic national roads[1].
In summer, the school holidays and the lighter traffic on some routes provide an opportunity to carry out more disruptive phases of works, launch new projects or undertake short-term operations. These works, planned to preserve as much mobility as possible for road users, are essential to maintaining a network that is safe, comfortable and free-flowing. As September begins, the following projects are worth highlighting:
- 12 projects have just been completed or are about to be completed;
- 9 new projects have recently started or will begin shortly;
- 15 projects that began before the school holidays are continuing.
Further projects will be announced in due course, as their start dates depend on various factors, including progress with administrative procedures, weather conditions and interactions with other works already under way.
Road users who want to keep up to date with works on Wallonia’s motorways and main national roads can visit the SOFICO website, www.sofico.org, where they can consult the interactive works map on the homepage and subscribe to the regional newsletter. They can also follow SOFICO on Facebook.
SOFICO would like to thank road users for their patience when they encounter these works on their journeys.
It also wishes to commend the outstanding work carried out by its technical partner, SPW Mobilité et Infrastructures, its own teams and the private companies appointed through public tenders, which enables these projects to go ahead and helps maintain a high-quality network for road users.
COMPLETED / SOON TO BE COMPLETED
1) E42/A15: work on 7 bridges between Fleurus and Heppignies towards Mons
Since early August, the right-hand lane and hard shoulder have been closed on the E42/A15 motorway between Fleurus and Heppignies to allow work on 7 bridges carrying the motorway. The speed limit is 70 km/h along this 6-kilometre stretch. The R3 slip road from Marcinelle towards the E42/A15 in the direction of Mons is also closed. A diversion is in place via the Muturnia roundabout.
The work involves repairs to the footways, surfacing and waterproofing on the slow-lane side of these structures.
The R3 slip road from Marcinelle towards the E42/A15 in the direction of Mons will reopen by the end of next week (5 September at the latest). The remaining works will be completed by the end of the following week (12 September at the latest).
Companies appointed through a public tender to carry out this project: RENOTEC GROUP & EUROVIA BELGIUM
1) E42-E19/A7: construction of a roundabout at exit no. 25, “Tertre”
This project, which began on 21 September 2020, involved building a roundabout at the junction of the exit slip road from exit no. 25, “Tertre”, on the E42/E19-A7 motorway towards France and the N547.
The new layout is intended to improve safety at this accident blackspot and reduce the tailbacks that form there at peak times, partly because of the proximity of several schools. A new exit slip road from the roundabout towards France has also been built. The roundabout opened to traffic on 18 December 2020. The final works were carried out in August to minimise disruption to traffic. The project will be fully completed on 27 August.
Company appointed through a public tender to carry out this project:
WANTY S.A.
Budget: €950,000 excluding VAT
2) E313/A13: resurfacing works between Vottem and Juprelle towards Antwerp
On 10 May, resurfacing works began on the E313/A13 motorway between the Vottem interchange and Juprelle, in the direction of Antwerp only. The project involves completely resurfacing the carriageway carrying traffic towards Antwerp and replacing the safety barriers.
The lanes between Vottem and Liers have been open since early July. Work has continued between Liers and Juprelle, where only one lane is available in each direction and the speed limit is reduced. On this stretch, all lanes towards Antwerp will be reopened by the evening of Friday 27 August at the latest. Traffic towards Liège will return to normal by 1September at the latest.
Company appointed through a public tender to carry out this project:
AB TECH S.A.
Budget: €2.7 million excluding VAT
3) E411/A4: resurfacing works under way between Wanlin and Lavaux-Saint-Anne towards Arlon
This project, which began on 26 February, involved resurfacing the E411/A4 motorway between Wanlin and Lavaux-Saint-Anne, from exit no. 22, Rochefort, to exit no. 22 A, “Lavaux-Saint-Anne”, a distance of approximately 7 kilometres, towards Arlon. The concrete traffic separators in the central reserve have been replaced.
The bridge over the Lesse has also been refurbished, with new waterproofing, surfacing and equipment, as has the trafficked section of the Wanlin service area. The lanes reopened on 20 July.
Planting in the central reserve is also planned for the appropriate season, around mid-October, and will take approximately two weeks. During these operations, 2 lanes will remain open in each direction, but traffic will be diverted and the speed limit reduced.
Company appointed through a public tender to carry out this project:
WILLEMEN INFRA S.A.
Budget: €9 million excluding VAT
4) R3, Charleroi: concrete repairs beneath the Eau d’Heure viaduct
Work on the Eau d’Heure viaduct, which carries the R3 near Montigny-le-Tilleul, has been under way since 12 July. Concrete repairs are being carried out beneath the viaduct. The work is therefore not visible from the structure itself, where one lane in each direction is closed for the duration of the project to accommodate the work platforms and for technical reasons relating to how the work is carried out.
The traffic management for these works is due to be removed on 31 August.
Company appointed through a public tender to carry out this project:
RENOTEC GROUP
5) N5/Route de Philippeville, Charleroi: resurfacing the Couillet roundabout
Work to resurface the Couillet roundabout, at the junction of the N5/R3/N572/rue des Haies/avenue de l’Armée française, began on Friday 20 August and lasted one week. Most of the work was carried out at night to minimise disruption. It will be completed on Friday 27 August.
Company appointed through a public tender to carry out this project: MICHAUX
Budget: €85,000 excluding VAT
6) N7/Chaussée de Lille, Tournai: resurfacing between Boulevard Bara and the Hertain roundabout
Work to resurface the Chaussée de Lille (N7) between Boulevard Bara and the Hertain roundabout has been under way since 5 July. The project has been divided into two phases.
Work is currently taking place on the N7 between the N7/Avenue Minjean junction and the Hertain roundabout. One lane remains open to road users travelling towards France. Traffic in the other direction, towards Tournai, is being diverted via the E429/A8 and N50.
It is not possible to access the side roads on the Froidmont side from the N7/Chaussée de Lille, or vice versa. The works will end on 3 September.
Company appointed through a public tender to carry out this project:
COLAS BELGIUM
Budget: €1.643 million excluding VAT
7) N40, Wellin: resurfacing between the N40/Rue Théodore Olix junction and the N40/Gongon junction
The resurfacing works between the N40/Rue Théodore Olix junction and the N40/Gongon junction, near the Coputienne housing estate, which had been under way since 19 August, were completed on 24 August.
Company appointed through a public tender to carry out this project:
Les Enrobés de Gerny
Budget: €132,590 excluding VAT
8) N50: upgrading the Ghlin section
This project to upgrade the N50 through Ghlin, over a distance of nearly 2 kilometres, began on 14 October 2019 and was divided into several phases to minimise the impact on traffic.
- Phase 1, 14 October 2019 to mid-June 2020: from the junction with avenue du Millénaire (excluding the junction) to the junction with rue Limauge (including the junction), a distance of approximately 1 km.
- Phase 2, 31 August 2020 to 14 June 2021: from the junction with rue du Grand Large (excluding the junction) to the junction with avenue du Millénaire (including the junction), a distance of approximately 1 km.
- Phase 3, 16 August 2021 to 21 August 2021: from the junction with rue du Grand Large (including the junction) to the Baudarts roundabout, a distance of approximately 300 m.
The final section affected by the works was therefore opened to traffic on Saturday 21 August 2021.
The project involved:
- Completely rebuilding the existing carriageway after demolishing it;
- Building a cycle lane in each direction;
- Constructing new footways;
- Reconfiguring the parking spaces on the residential side;
- Repairing the drainage system and private connections (SPGE);
- Repairing the water distribution pipes and private connections (SWDE).
Company appointed through a public tender to carry out this project:
WANTY S.A.
Budget: €6.27 million excluding VAT, funded by
- SOFICO: €3,753,000 excluding VAT
- the City via SPGE: €1,941,000 excluding VAT
- SWDE: €576,000 excluding VAT
9) N89: resurfacing between Vecmont and La Roche-en-Ardenne
This project, which began on 12 April, involved resurfacing the N89 in both directions between Vecmont and La Roche-en-Ardenne, excluding the section through Beausaint. The works covered nearly 6 kilometres in total and included local deep repairs to the road, in some cases down to the foundation, as well as resurfacing.
In addition, on the section from the exit from Beausaint to the centre of La Roche, safety barriers were installed on some bends and a counter-thrust strip was built. This structure looks like a flat drainage channel and prevents lateral movement of the road structure. The project was completed on 5 July.
Company appointed through a public tender to carry out this project:
DEUMER S.A.
Budget: €1.7 million excluding VAT
10) N90, Ivoz-Ramet: resurfacing the Horre roundabout
Work to resurface the roundabout known as “de la Horre” on the N90 in Ivoz-Ramet began on 17 May. The works are intended to treat the roundabout’s entry and exit lanes to prevent asphalt ridges from forming. The N90’s surface course is also being replaced near the roundabout in the Seraing-Huy direction.
During the works, traffic will be restricted to one lane in each direction, with a speed limit of 50 km/h. It will no longer be possible to access the N90 from Rue de la Horre or from the exit of the Ivoz-Ramet industrial estate, in either direction. Traffic will be diverted via the N644 and N90.
The road will reopen on 3 September.
Contractor appointed through a public procurement procedure:
COLAS BELGIUM
Budget: €337,507 excl. VAT
11) N912: La Bruyère: construction of a roundabout at the junction of the N912, Rue du Chainia and Rue du Vieux Raucourt
This project involved constructing a roundabout at the junction of the N912, Rue du Chainia and Rue du Vieux Raucourt. The new infrastructure is designed to make the junction safer and improve traffic flow. The roundabout opened to traffic on 11 August.
In the coming weeks, the temporary road signs will be replaced with permanent signage. The existing lighting will be replaced with LED lighting as part of the Plan Lumières developed by SOFICO and its private partner LuWa. The pedestrian and cycle crossings will be installed at the end of September, once the surfacing has had time to settle. These operations will have only a very limited impact on traffic.
From August to November 2020, utility works associated with the project were carried out. The works were then suspended and the roads reopened for the winter period, before the main project got under way on 12 April.
Contractor appointed through a public procurement procedure:
COLAS BELGIUM
Budget: €794,000 excl. VAT
NEW PROJECTS
1) Liège: E25-E40/A602 link: repair works following the July floods
The link is continuing to reopen gradually: from mid-October, it will once again be possible to travel along its entire length, subject to certain conditions.
The section between interchange 38, “Angleur/Grosses-Battes/Belle-Ile”, and interchange 37, “Val-Benoît/Seraing/Marche”, will once again be open to traffic, subject to restrictions on traffic conditions, including the number of lanes and the speed limit, as required for safety. The conditions for this section, as well as for the rest of the link, will be set at the end of September, depending on progress with the repair works.
This is the last section of the link to remain closed following flood damage. The electricity, lighting, cameras, dynamic signage and ventilation systems are no longer operational, meaning the minimum safety requirements under the European Mont Blanc Directive 2004/54/EC can no longer be met.

With mobility needs in mind, the SOFICO and SPW MI teams are working intensively to organise this gradual reopening as quickly as possible while ensuring the necessary safety conditions for road users.
More information: 210818-a602-ouverture-valbenoit-gb-mode-degrade-cp-1.pdf (sofico.org)
Budget: At present, the works required across the link following flood damage to allow it to reopen under restricted conditions in mid-October are estimated to cost more than €2 million excl. VAT
2) E25/A26: resurfacing between Les Tailles and Houffalize towards Neufchâteau
Resurfacing works on the E25/A26 began on 18 August between Les Tailles and Houffalize. They affect only the carriageway towards Neufchâteau.

Until the end of September, one lane will remain open in each direction on the E25/A26 between Les Tailles and Houffalize, with a speed limit of 70 km/h.
During this period, drivers heading towards Neufchâteau will no longer be able to access the Nutons motorway service area.
In addition, at interchange 51, “Houffalize”, for the duration of the works:
- Drivers heading towards Neufchâteau will no longer be able to use the exit slip road to the N30.
- A diversion will be in place via interchange 52, “Mabompré”.
- Drivers travelling on the N30 from Houffalize will no longer be able to join the motorway directly towards Neufchâteau.
- A diversion will be in place via interchange 52, “Mabompré”.
Finally, also at interchange 51, “Houffalize”, for a few days at the very end of the works:
- Drivers travelling on the N30 from La Baraque de Fraiture will not be able to join the motorway directly towards Neufchâteau (shown in blue on the map).
- A diversion will be in place via interchange 52, “Mabompré”.
Contractor appointed through a public procurement procedure: SOCOGETRA S.A.
Budget: more than €2.385 million excl. VAT
3) E25-E411/A4: resurfacing between Rulles and Habay towards Luxembourg
On Wednesday 1st September, resurfacing works will begin on the E25-E411/A4 between Rulles and Habay, a distance of 6.4 km. They will affect only the carriageway towards Luxembourg.
From 1st to 30 September, the speed limit will be 70 km/h in both directions on the E25-E411/A4 between Rulles and Habay.
Towards Luxembourg:
- traffic will be restricted to one lane, diverted onto the left-hand carriageway, which normally carries traffic towards Brussels;
· the exit slip road and motorway entrance at interchange 28A, “Rulles”, will be closed. A diversion will be in place via interchange 29, “Habay”.
- the Nantimont rest area will be inaccessible.
Towards Brussels:
- two lanes will remain open, diverted onto the right-hand lane and hard shoulder;
- interchange 28A, “Rulles”, and the Nantimont rest area will remain accessible.

The road is expected to reopen at the end of September 2021, weather permitting.
Contractor appointed through a public procurement procedure: SOCOGETRA S.A.
Budget: more than €1.534 million excl. VAT
4) Lincent: E40/A3: resurfacing towards Liège
The project will involve resurfacing just over 4 kilometres of the E40/A3 at Lincent, towards Liège. Work will start in mid-September and finish in early November 2021. Traffic will be reduced to 2 lanes in each direction, with a speed limit in place.
Contractor appointed through a public procurement procedure: BAGUETTE
Budget: more than € 1.469 million excl. VAT
5) E42/A15: resurfacing between Horion-Hozémont and Saint-Georges towards Namur
The works will resurface the central and left-hand lanes of the E42/A15 between the Horion-Hozémont viaduct and Saint-Georges, towards Namur only. They will start on 13 September and finish on 17 September. During the works, traffic towards Namur will be reduced to 2 lanes, with a speed limit in place.
Contractor appointed through a public procurement procedure: BAGUETTE
Budget: more than €238,300 excl. VAT
6) E42/A15-Wanze: refurbishment of the Huccorgne viaduct
The first phase of the major refurbishment of the Huccorgne viaduct, which carries the E42/A15 at Wanze, began on 2 August. This phase involves installing reinforcements beneath the bridge carrying the carriageway towards Namur, so that it can accommodate 2X2 lanes during the next phase of the project. It will be completed on 5 December.

During this phase, as during those that follow, 2 lanes will remain open in each direction on the motorway, with a speed limit of 50 km/h.
The project is divided into 3 main phases (4 months, 6 months and 6 months), scheduled to run through to July 2023, with the roads reopening in the second half of 2022.
Below the motorway, Rue Robiewez and Rue Famelette have been closed since 2 August 2021 and will remain closed until 2 August 2023.
- A diversion is in place via the N652/Route de l’Etat, Route de Lavoir and Rue Biénonsart
In practical terms, the works will give the viaduct a new lease of life:
Ø Both approach spans will be demolished and rebuilt, except for the piers, which will be retained and repaired;
Ø The central section will be refurbished;
Ø The project also includes installing new waterproofing and surfacing on the viaduct, as well as noise barriers, and more.
More information: https://sofico.org/app/uploads/2021/06/210622-e42a15-viaduc-de-huccorgne-rehabilitation-lancement-cp.pdf
Contractors appointed through a public procurement procedure: temporary association BAM GALERE-BESIX
Budget: more than €23 million excl. VAT
7) N40: Libin: two weeks of resurfacing between the Transinne roundabout and the Galaxia roundabout
Resurfacing works on the N40 between the Transinne roundabout and the “Galaxia” roundabout, by the Euro Space Center industrial estate, will begin on Monday 30 August. To minimise disruption to traffic, the works will be carried out in two phases and will finish on Friday 10 September.

Phase 1, Monday 30 August to Friday 3 September:
On the N40, from Namur towards Arlon, between the “Galaxia” roundabout and interchange 24, “Transinne”, on the E411/A4, inclusive, traffic will be controlled by traffic lights.
Drivers travelling on the E411/A4 from Namur will no longer be able to use exit slip road 24, “Transinne”.
- They will be diverted via interchange 23, “Tellin”.
Phase 2, Monday 6 September to Friday 10 September:
The N40 will be closed to traffic between interchange 24, “Transinne”, on the E411/A4, not including the interchange itself, and the Transinne roundabout.
- Drivers will be asked to follow the local diversions via Maissin and Libin.
Contractor appointed through a public procurement procedure: Les Enrobés de Gerny
Budget: €245,000 excl. VAT
8) N60: safety works between Thieulain and Leuze-en-Hainaut
Works to improve safety on the N60 between Leuze-en-Hainaut and Thieulain began on Monday 23 August. The works, scheduled to finish in mid-October, are divided into two phases and will repair a culvert beneath the national road and create a cycle path.

Phase 1, from 23 August to mid-September, on the N60:
Traffic is prohibited in both directions between the junction of the N60 and Warde and the Croix-au-Mont roundabout, while the culvert is repaired.
- Diversions are in place through the village of Thieulain.
Phase 2, from mid-September to mid-October, on the N60:
Traffic between the Croix-au-Mont roundabout and the junction of the N60 and Planche à Leuze will be one-way, towards Frasnes-lez-Anvaing only. The works will involve building a cycle path along approximately 200 metres of this section.
- Drivers travelling from Frasnes-lez-Anvaing towards Leuze-en-Hainaut will be diverted through the village of Thieulain.
9) N89: Libramont: preparatory works for future safety improvements at the Recogne industrial estate
Preparatory works lasting several months began on Tuesday 17 August in Recogne, on Rue de Saint-Hubert (N89), between the junction with Rue de Tibétême (N826A) and the railway bridge over the national road. This is a preliminary stage ahead of a project due to start in spring 2022, which will improve safety in the area by building a roundabout, modernise it and adapt access to the neighbouring industrial sites.

From 17 August until the end of 2021, utility relocation works will be carried out on rue de Saint-Hubert (N89), between the junction with Rue de Tibétême (N826A) and the railway bridge over the national road towards Saint-Hubert. During these operations:
- One lane will remain open in each direction on the N89, with the speed limit set at 50 km/h;
- Access to the business park will remain open.
The main works will begin in spring 2022 and finish at the end of June 2022. The precise dates, phasing and related changes to traffic conditions will be announced at a later date. The works will involve:
- Building a roundabout 60 metres in diameter, with 6 entries, at the junction of the N89 and rue de Tibétême (N826A);
- Creating access roads to various companies, including L’oréal and Solarec (which handles 300 lorries a day);
- Rehabilitating and upgrading the N89 between the roundabout and the railway bridge.
Contractor appointed through a public tender for the works: DANIEL PIROT ET FILS S.A.
Budget: €1.854 million excluding VAT
WORKS ALREADY UNDER WAY BEFORE THE HOLIDAY PERIOD
1) E40/A3: Asbestos removal from the bridge over the motorway at Orp-Jauche
Asbestos removal works on the bridge over the E40/A3 motorway at Orp-Jauche began on 6 August. They are due to finish around mid-October.
Two lanes will remain open in each direction, with the maximum speed limited to 70 km/h:
• first, the left-hand and middle lanes will remain open;
• then, traffic will use the right-hand lanes and the hard shoulders.
A LIDAR speed camera is regularly deployed to encourage drivers to slow down and monitor their speed.
These works are part of a project to remove asbestos from 6 overbridges on the E40/A3 motorway between Hélécine and Remicourt.
The bridges are being treated one at a time, starting at Hélécine and moving towards Remicourt, to minimise the impact on traffic. The bridges concerned, in order of treatment, are located:
- at exit 26, “Hélécine” (bridge 56);
- at Orp-Jauche (bridge 58);
- at Lincent (bridge 66);
- at exit 28, “Berloz” (bridge 76);
- at Rosoux-Crenwick/Berloz (bridge 77);
- at Remicourt (bridge 89).
The bridge at Hélécine was treated from 26 February to 14 May 2021.
The bridge at Lincent is also expected to be treated in 2021, with the final three bridges scheduled for 2022.
Asbestos removal is an essential step ahead of the future rehabilitation of these bridges. These complex works require the installation of a sealed enclosure that moves forward as the works progress, and staff must wear protective suits.
Contractors appointed through a public tender for the works:
REDECO: LAURENTY BATIMENTS SM
Budget: €1.3 million excluding VAT
2) E42/A15: Rehabilitation works on the bridge at the Houdeng-Goegnies interchange over the motorway
Rehabilitation works have been under way since 8 June on the bridge at interchange 20, “Houdeng-Goegnies”, which crosses the E42/A15 motorway.
Drivers can still join or leave the motorway at this interchange. There is no impact on the motorway itself. However, the bridge over the motorway (Chemin de Familleureux) is closed to traffic. Diversions are in place.
The study and planning of some of the works to be carried out on the structure are still under way, so it is not yet possible to set a reopening date.
Contractor appointed through a public tender for the works:
A2 S.A.
3) E411/A4, interchange 8A: construction of a direct link between the motorway and the P+R car park
The first stage of a major project to deliver substantial mobility improvements in Louvain-la-Neuve, close to exits 8A of the E411/A4 motorway and the P+R car park, began on 4 February 2019. The works will improve traffic flow in the area by avoiding conflicting movements, notably through the creation of direct links between the P+R car park and the nearby main roads. This major project is divided into three parts.
Part I covers the section between the E411/A4 motorway (excluding the bridge) and the P+R car park.
It involves:
· A direct link from the motorway exits to the P+R car park.
Thus, traffic coming from Brussels, once on boulevard du Brabant wallon (interchange 8A), will have two lanes: the right-hand lane will lead to the N4 roundabout, while the left-hand lane will provide direct access to the P+R car park.
Traffic coming from Namur will follow the same principle after crossing the motorway bridge: the road will split into two lanes, with the left-hand lane leading to the N4 roundabout and the right-hand lane providing direct access to the P+R car park.
Creating this direct link will require the construction of 2 box culverts:
o Box culvert 1: to pass beneath two lanes, one running from the N4 roundabout to the motorway and the other linking the motorway from Namur to the roundabout;
o Box culvert 2: to pass beneath the N4.
· Two lanes to leave the P+R car park and head towards the motorway access roads, passing beneath the N4.
· A bypass providing direct access from the N4, for traffic coming from Mont-Saint-Guibert, to the motorway access roads.
· Relocation of the cycle path along boulevard du Brabant wallon, as well as a third box culvert to allow pedestrians and cyclists to pass safely beneath the motorway slip road (box culvert 3).
· The foundations for a fourth box culvert, to allow avenue Jean Monnet to be extended beneath boulevard du Brabant Wallon in a few years’ time.
As part of these works, from 2 August until 3 September, traffic on the E411/A4 towards Namur or Brussels will be unable to use exits 8A, “Louvain-la-Neuve”. A diversion is in place via the neighbouring interchanges 8 and 9. This closure will allow the slip roads to be adapted to the new layout.
These operations will complete phase I, and the traffic signs will be removed from this section by 4 September. Only very occasional disruption is expected afterwards, while finishing works are carried out.
Phase I has a budget of nearly €5 million excluding VAT, broken down as follows:
€3.77 million funded by SOFICO;
€450,000 funded by SPW Mobilité et Infrastructures;
€760,000 funded by IBW as part of preparations for the box culvert that will later allow avenue Jean Monnet to be extended.
Part II involves creating an exit from the P+R car park onto boulevard de Wallonie towards Louvain-la-Neuve. It covers the area west of the N4 roundabout.
Work began in early 2021 and is expected to take around a year.
It involves:
· An exit from the P+R car park onto boulevard de Wallonie, requiring the boulevard to be shifted to the current central reservation and the bypass from the N4 coming from Wavre to be adjusted.
· A new bus stop.
· Safe pedestrian crossings on boulevard de Wallonie near the roundabout.
This part of the project, managed and funded by SPW Mobilité et Infrastructures, has a budget of over €1.3 million. The new bus stop will be funded by OTW, at a cost of around €18,700.
Part III will involve widening the bridge over the E411/A4 motorway, which connects the access and exit from Namur to Boulevard du Brabant wallon, to provide a safe crossing for pedestrians and cyclists. The bridge will also be renovated, including renewal of its waterproofing membrane.
This final phase is included in the 2020-2026 Mobility and Infrastructure Plan. The public tender procedure has yet to be carried out.
4) E411/A4, Beez: Rehabilitation of Pont Collard, linking the E411/A4 to the N90 towards Jambes
A project to rehabilitate Pont Collard, which carries exit slip road 15, “Loyers”, linking the E411/A4 to the N90, began on 15 March.
The works involve rehabilitating the structure that carries the slip road over the N90, down to its concrete deck, including its waterproofing. They also include:
- rehabilitating the retaining walls by removing the concrete surface and rebuilding them;
- renewing the surfacing on the 2 ramps, from the E411/A4 to the N90 towards Jambes and from the N90 coming from Andenne to the E411/A4, as well as on their pavements, and replacing the safety barriers.
Since early May, the works have focused mainly on repairing the bridge:
- A diversion is in place for traffic coming from the E411/A4 and heading to Jambes. Drivers should follow signs for Andenne, make a U-turn at a temporary roundabout to be built at the junction with rue de Loyers, then head back towards Jambes via the ramps alongside the N90 near the Beez viaduct.
- Traffic on the N90 coming from Andenne and heading for the E411/A4 must follow a diversion via the pont des Grands Malades.
Traffic on the ramps is limited to 50 km/h.
The works, initially expected to finish in mid-November 2021, are now expected to be completed earlier than planned, at the end of next September.
Contractor appointed through a public tender for the works:
BAM GALERE
Budget: over €1.9 million excluding VAT
5) E420/N5: Construction of a covered cutting at Frasnes (Couvin bypass)
Construction of this underpass beneath the railway line at Frasnes-lez-Couvin is the third phase of the Couvin motorway bypass and the only phase still under way. It involves building a structure around 800 metres long, including an 80-metre tunnel, to carry the E420/N5 beneath the railway line as a 2x2-lane road. Work began on 3 October 2016. Traffic has been able to use a 2x1-lane configuration since 7 June 2019.
From 25 June until the end of the works, traffic on the E420 through the covered cutting at Frasnes-Lez-Couvin will use the half of the cutting that will eventually carry traffic towards Charleroi, with one lane in each direction. The speed limit there is 50 km/h.
Drivers travelling on the E420 towards France can no longer use the “Couvin nord: Chimay” exit slip road to reach the N5 via the Locomotive roundabout.
A diversion is in place via the next exit, “Couvin centre, Viroinval, Petigny”, for all traffic. Heavy goods vehicles heading for Chimay via the N99 cannot travel through the centre of Couvin. They should make a U-turn at the “Couvin centre, Viroinval, Petigny” interchange, rejoin the E420 towards Charleroi and take the “Couvin nord, Chimay” exit slip road.
Next autumn, both halves of the cutting will open to traffic, with 2 lanes in each direction. However, finishing works will still be required, including the installation of signs, kilometre markers and cladding, occasionally requiring one lane to be closed. These finishing works are expected to be completed by the end of 2021, marking the completion of the Couvin motorway bypass project.
Contractor appointed through a public tender for phase III:
JAN DE NUL
The total cost of the Couvin motorway bypass project is expected to be around €180 million excluding VAT, funded by SOFICO with the help of an €80 million repayable loan granted by the EIB.
6) E429/A8 towards Tournai, Enghien: safety improvements at junction 25 “Hoves/Petit-Enghien”
Work began on 5 October last year to upgrade junction 25 “Hoves/Petit-Enghien” (Enghien) on the E429/A8 towards Tournai. The aim is to improve safety in this particularly accident-prone area when joining the motorway.
Specifically, the work involves:
building a roundabout at the junction of the N285 and the exit slip road at junction 25 “Hoves/Petit-Enghien” towards Tournai;
building a new access slip road from the N285 to the E429/A8 towards Tournai and demolishing the old one;
extending the merge lane onto the E429/A8 from the N285 towards Tournai and lengthening the deceleration lane for exit 26 “Enghien”.
From 5 October 2020 until October 2021:
Ø on the E429/A8 towards Tournai, only one lane will remain open between junctions 25 “Hoves/Petit-Enghien” and 26 “Enghien”, with the speed limit set at 70 km/h;
Ø towards Tournai, exits 25 and 26 for “Hoves/Petit-Enghien” and “Enghien” will remain accessible. Access to the motorway towards Tournai from junction 25 “Hoves/Petit-Enghien” will only be possible via the nearby roundabout;
Ø on the N285, one lane will remain open in each direction, with the speed limit set at 50 km/h.
Budget: €2.88 million excluding VAT
Contractor appointed through a public tender for this project:
EUROVIA BELGIUM
7) N4, Arlon: construction of a roundabout at the Liedel junction
Work at the Liedel junction in Arlon, where the N4, rue Godefroid Kurth and avenue de Mersch meet, began in 2019.
The project aims to improve safety and traffic flow, active travel (pedestrians and cyclists), and the appearance of the N4. It involves:
- Building a roundabout to replace the traffic-light-controlled junction;
- Improving safety on the N4 by reducing the roundabout area from 2×2 lanes to 2×1 lane;
- Landscaping the nearby central reservation with green spaces;
- Installing a cycle path on both sides of the N4;
- Providing parking spaces (25) on both sides of the roundabout;
- Installing LED lighting in the area;
- Placing the monument to Lieutenant Félix-Louis Liedel in the middle of the roundabout.
Since 23 August last year, only work with short-term, localised effects on traffic remains to be completed: construction of the central island on the lanes towards Bastogne, work on the verges on the rue Godefroid Kurth side, and planting.
The project is expected to be completed by the end of 2021. To ensure the road markings last, a final operation will be carried out in spring 2022.
Contractor appointed through a public tender for this project:SOCOGETRA
Budget: €1 million excluding VAT
- More than €880,000 excluding VAT funded by SOFICO
- More than €180,000 excluding VAT funded by the City of Arlon (pavement works)
- More than €20,000 excluding VAT funded by SRWT (new bus stop)
8) N4: upgrading the Tenneville crossing
Temporary safety measures were introduced on the Tenneville crossing several years ago, including reducing traffic to one lane and lowering the speed limit to 70 km/h. This helped reduce the number of fatal accidents on this stretch.
Work began on 31 March 2019 to make these measures permanent and ensure the safety of road users and local residents, for whom this road remains a dangerous area.
Specifically, the work involves:
resurfacing around 4 kilometres of the Tenneville crossing;
replacing the temporary road-narrowing measures with a larger central island, marking out one lane in each direction. The island will be traversable at numerous points to allow people to cross from one side of the road to the other;
upgrading the sewer network and reviewing the surface water drainage system.
Since early July, work has been taking place in the central section, between the 2 traffic lanes. Traffic is now using its permanent alignment along the full length of the road, with the speed limit set at 50 km/h.
During the 2nd half of September, the N4 will be closed in one direction at a time overnight (for 2 to 3 nights in each direction) for a week at the work site, so that the surface course can be laid across the entire project area, minimising the impact on traffic. Diversions will be in place.
Throughout the works, heavy goods vehicles over 3.5 tonnes are strongly advised to use the diversion from Barrière de Champlon to Barrière Hinck via the N89, N848 and N826. Heavy goods vehicles on long-distance journeys are advised to use the E411/A4 and E25/A26.
Businesses will remain accessible, and residents will of course retain access to their homes. They will be informed in good time about the few days of asphalt works when they will be unable to use the road.
The project is expected to be completed by autumn 2021.
Budget: more than €12.12 million excluding VAT, funded by
- SOFICO (around €10 million excluding VAT);
- Tenneville Municipality, which is contributing to the cost of the surface water drainage works and landscaping, and will also install new drinking water pipes at a cost of almost €1 million excluding VAT;
- SPGE, which is funding the sewer network upgrade and the installation of new connections at a cost of more than €992,000 excluding VAT;
- OTW, which will upgrade eight bus stop areas at a cost of more than €185,500 excluding VAT.
9) N50, Saint-Ghislain: demolition of the bridge over the Darse bottleneck at Hautrage
The bridge over the Darse bottleneck at Hautrage (N50, Saint-Ghislain) was demolished on 2 December 2019. Reconstruction of the bridge began in February 2020.
The steel structure of the bridge was installed on 26 January this year. Since then, the precast elements of the permanent formwork have been put in place. The teams have carried out the reinforcement work, placing the “reinforcing bars” before casting the top slab. The slab has now been cast.
Waterproofing for the bridge is due to be installed in the coming days, weather permitting (the deck must be dry for this operation).
Work will then continue with the installation of surfacing and various fixtures, followed by resurfacing the N50 for around 100 metres on either side of the structure.
As a reminder, the bridge over the Darse bottleneck at Hautrage (N50, Saint-Ghislain) has been closed to traffic since 26 February 2019. It carries 8,500 vehicles and 500 heavy goods vehicles a day.
Following inspections of structures in early 2019, it emerged that three bridges (SPW-SOFICO) dating from the 1950s had to be closed to traffic because they had significant defects, mainly affecting the cables embedded in the concrete that ensure the bridges’ stability (post-tensioning cables).
This new structure is expected to be completed by the end of 2021.
Contractor appointed through a public tender for this project:SOCOGETRA
Budget: €3.8 million excluding VAT
10) N50: safety improvements and rehabilitation between Pecq and Warcoing
Work to improve safety and rehabilitate around 5 km of the N50, between the entrance to Pecq (at the rue de Bailleul/chemin de la Garenne junction) and the Pont Bleu roundabout (border with Flanders), began on 1 March this year. It is divided into three sections.
PHASE 1
Since 1 March, the works have affected the section between the exit from Pecq (towards Flanders, beyond the junction with rue de Saint-Léger/Bas Chemin) and the Pont Bleu roundabout, a distance of around 3.5 km.
- BETWEEN THE 4 MOULINS ROUNDABOUT (excluding) AND THE PONT BLEU ROUNDABOUT (excluding)
- This section is due to reopen in early September. However, the Pont de l’Espierre cannot reopen and will remain under construction until the end of October.
- Traffic, currently closed in both directions along the entire section, will only be cut off at the Pont de L’Espierre.
- The diversion currently in place via the N512 and N353 (Warcoing and Espierre) will remain in place for through traffic.
- BETWEEN THE RUE DE SAINT LEGER/BAS CHEMIN JUNCTION AND THE 4 MOULINS ROUNDABOUT (included)
- This section is expected to reopen next October.
- One direction of traffic will remain open, towards Pecq, with the speed limit set at 50 km/h. Vehicle access will be maintained for residents, businesses and restaurants.
- A diversion is in place for road users travelling towards Flanders via rue Albert 1er, then rue de la Croix rouge and route Fluviale.
PHASE 2
The second phase, covering the built-up area of Pecq, will run from the junction of the N50 with rue de Bailleul and chemin de la Garenne to the junction of the N50 with rue de Saint Léger/Bas Chemin. This phase is scheduled for next year, in 2022, after the winter.
The project involves rehabilitating the road along the entire section and includes measures to improve safety for all types of road user.
In the built-up area of Pecq:
- Side islands, partly landscaped with vegetation, will be installed on the road at the town entrances and exits to create a “gateway effect” and slow traffic. The central islands will be redesigned;
- Pavements will be widened at pedestrian crossings and continuous pedestrian routes will be provided. Bus stops will be upgraded;
- Shared pedestrian and cycle crossings will be provided.
Along the rest of the section:
- The road will be reduced from 4 lanes to 3;
- A two-way cycle path separated from the road by a safety barrier will be built;
- The bridge carrying the N50 near the Pont Bleu roundabout will be rehabilitated;
- Landscaping will be carried out at the Pont Bleu and 4 Moulins roundabouts.
Contractor appointed through a public tender for this project:S.A. TRBA
Budget: €3.8 million excluding VAT
11) N89, Paliseul: rehabilitation of the Plainevaux bridge over the national road
Work to rehabilitate the Plainevaux bridge (bridge 3), which carries rue Saint-Hubert over the N89 near Paliseul, has been under way since Monday 15 March.
Specifically, the work involves:
- Installing new waterproofing, surfacing, concrete pavements and parapets on the structure;
- Replacing the bridge bearings;
- Rehabilitating the structure and applying a protective coating.
- Replacing the safety barriers along the centre line of the N89.
This work will have no impact on the N89. However, traffic may be reduced to one lane in each direction for short periods.
The bridge itself is closed to traffic. Diversions are in place via the neighbouring junctions.
Contractor appointed through a public tender for this project:
Joint venture “4m Engineering: 4m Europe”
Budget: €567,000 excluding VAT
12) N90: rehabilitation works between Andenne and Namur
This project to improve safety and rehabilitate the N90 road surface between Andenne and Namur, which began on 28 September 2020, aims to:
- Reduce the road from 2×2 lanes to 2×1 lane
- Rehabilitate the surface course in both directions over 4 km
- Create right-turn and left-turn lanes by installing road markings and central islands
- Upgrade vertical signage and speed limits (signs and road markings).
On 6 November 2020, the N90 was fully reopened in both directions.
From Tuesday 15 June to 10 July 2021, work was carried out in succession on two sections of the road:
- Over approximately 3 km, from Rue Gawday to Maizeret (N90);
- On Chaussée d’Anton (N90) in Andenne, over approximately 2 km (asphalt laying).
Due to adverse weather conditions, the construction of the islands on Chaussée d’Anton (N90) in Andenne could not be completed in July as planned. The final phase on Chaussée Moncheur (N90) in Andenne could not be carried out in August.
Traffic has therefore been moving under normal conditions along this section since 10 July.
Work will still be required at a later date, to be determined, to construct islands:
- on Chaussée d’Anton (N90) in Andenne, over approximately 2 km.
- on Chaussée Moncheur (N90) in Andenne, over less than a kilometre, using traffic lights.
During this work, traffic is expected to be controlled by traffic lights.
Contractor appointed through a public tender to carry out this project:
WILLEMEN INFRA
Budget: €2.184 million excluding VAT
13) N90: Road improvements as part of the enlargement of the Ampsin-Neuville lock complex
Work to improve safety and alter the alignment of the N90 began in August 2018 between the Tihange roundabout and the area upstream of the village of Ombret, as part of the enlargement of the Ampsin-Neuville lock complex.
Since mid-June 2020, road users travelling on the N90 between Ombret and Tihange have been able to use part of the new road built following the enlargement of the lock complex. This new section has one lane in each direction, but is ultimately intended to carry traffic heading towards Liège only. The opposite carriageway, towards Huy, is still under construction. The roundabout has also been partially built and will be opened when the second section of the road is complete.
The work aims to:
· Alter the alignment of the N90 following the widening of the lock exits, to allow the Ampsin-Neuville lock complex to accommodate larger vessels;
· Improve the safety of the national road by designing the layout to encourage road users to reduce their speed:
o by providing one lane in each direction and a hard shoulder throughout, with a speed limit of 70 km/h;
o by creating right-turn lanes and acceleration lanes at adjoining roads and the lock complex;
o by building a new roundabout upstream of the village of Ombret;
o by constructing a central reservation between this new roundabout and the lock complex;
o by improving cycle links (in particular, by eventually closing Grand Route to motor traffic and reserving it for cyclists and pedestrians).
During the works, traffic on the N90 will use one lane in each direction, with a reduced speed limit. (A weekend closure will need to be scheduled in 2022 to install the extension of the dam footbridge over the N90.)
Access to Grand Route from the N90 at Ombret remains via Ombret Bridge. Stops on TEC bus route 9 on Grand Route in Ombret remain in service.
During the works, the RAVeL route will remain continuous via the left bank. Cyclists travelling from Tihange towards Liège can use a lane on Ampsin Bridge, the right-turn lane, which is reserved for them.
Roadworks on the N90 are expected to be completed by the end of 2021, subject to weather conditions.
Work on the lock complex began on 1er August 2018. A symbolic first spade in the ground ceremony was held in the presence of the authorities on 4 September 2018. The aim is to bring the large lock (225X25 metres) into service at the end of 2023.
The works to enlarge the lock complex, including the N90 works, were awarded for a total budget of approximately €138 million excluding VAT, funded by SOFICO with the support of a repayable loan granted by the EIB and a grant from the European Commission.
14) N90: Octroi de Bray
Since 15 March, preparatory work has been under way in Estinnes and Binche, at the intersection of the N90/Route de Mons and the N27/Avenue Léopold III, ahead of the forthcoming works to build a roundabout at Octroi de Bray.
The work includes relocating utility services and removing islands on the N90 so that traffic can be maintained during the main works. These operations have only a very limited impact on traffic: one lane remains open in each direction on the N90, and the N90-N27 connection will remain open. This preparatory phase will be completed shortly, allowing the main works to begin during September. Further information will be provided in due course.
The project will specifically involve:
building a roundabout at the junction of the N90 and N27 to improve safety and traffic flow in the area;
catering for active travel by creating shared pedestrian and cycle crossings;
refurbishing two bus stops on the N90, on either side of the roundabout, and making them accessible to people with reduced mobility.
In addition, to minimise disruption for road users, the works have been coordinated with a project being carried out on behalf of SPGE to install a sewer collector beneath the N90.
Following this work, the N90 surface will also be renewed over 600 m from the new roundabout towards Mons.
Contractor appointed through a public tender to carry out this project: WANTY
Budget: €3 million excluding VAT, funded by
- SOFICO, contributing almost €1.905 million excluding VAT;
- SPGE, contributing approximately €1 million.
15) N243: refurbishment and safety improvements between Wavre and Chaumont-Gistoux
Refurbishment and road improvement works began on the N243/Chaussée de Huy on 1er March. The project covers a 5 km section from the “des 4 sapins” roundabout (junction of the N243/Avenue Molière/Venelle des Cèdres) in Wavre to the Intermarché in Chaumont-Gistoux. It is divided into several phases.
Currently and until 10 September, between Rue du Moulin and Carrefour Tout Vent (excluding the junction):
- Traffic on Chaussée de Huy is only permitted in the direction of Wavre.
- Road users travelling along Chaussée de Huy towards Perwez are diverted via the N25 and E411/A4.
On 11 September, between Rue du Moulin and Chemin de l’Herbe:
- Traffic will be completely prohibited in both directions while the road surface is laid.
- Road users will be diverted via the N25 and E411/A4.
From 30 August to 4 October, from the 4 Sapins roundabout (inclusive) to the junction with the N25 (including the interchange)
- Traffic on Chaussée de Huy will only be permitted in the direction of Wavre.
- Road users travelling along Chaussée de Huy towards Perwez will be diverted via Chemin de Vieuxsart, then the N25
From 13 September to the end of October, at the Tout Vent junction:
- Traffic on the N243 will be controlled by traffic lights.
- Side roads will be closed, with local diversions in place.
Finally, the section of the N243 between the junction with Allée de la Frênaie and the 4 Carrés junction, excluding the latter, will be completed in spring 2022.
The project aims to:
- Thoroughly renew the N243/Chaussée de Huy road surface in both directions, from the “des 4 sapins” roundabout (junction of the N243/Avenue Molière/Venelle des Cèdres) in Wavre to the Intermarché in Chaumont-Gistoux;
- Completely refurbish the cycle track;
- Widen and improve the safety of two junctions by adding left-turn lanes for both directions of travel:
- at the junction of Chaussée de Huy, Rue and Chemin Tout Vent;
- at the junction of Chaussée de Huy, Rue des Quatre Carrés, Chemin de l’Herbe and Rue Arsène Matton;
- Refurbish the 10 bus stops and make them accessible to people with reduced mobility.
Contractor appointed through a public tender to carry out this project: VIABUILD
Budget: almost €3,000,000 excluding VAT, broken down as follows:
- €2.911 million excluding VAT funded by SOFICO;
- €80,000 excluding VAT funded by OTW (for the construction of the 10 bus stops).