Upgrading the Ampsin-Neuville lock site to large-gauge navigation: the large-gauge lock is taking shape!

Upgrading the Ampsin-Neuville lock site to large-gauge navigation: the large-gauge lock is taking shape!

Since January 2022, work to upgrade the Ampsin-Neuville lock site to large-gauge navigation has focused on building its large-gauge lock (225 x 25 metres, capacity: 9,000 tonnes). SOFICO and its partners provide an update on this major project. The new infrastructure is due to enter service in the first quarter of 2024. The public will be able to visit this huge construction site on 7 May as part of the Open Construction Sites Day.

On 18 January 2022, the new medium-gauge lock at the Ampsin-Neuville site (225 x 12.5 metres, capacity: 4,500 tonnes) officially opened to navigation. This ensured that vessels could continue to pass while work focused on building the adjacent large-gauge lock (225 x 25 metres, capacity: 9,000 tonnes), the project’s ultimate objective. 

Since then, the first stages of work have involved demolishing the old lock and constructing the concrete elements of the infrastructure, a task that is still under way.

Work schedule:

  • January 2022: Demolition of the old lock begins;
  • June 2022: Concrete works on the infrastructure begin;
  • Mid-May 2023: Installation of the upstream and downstream gates;
  • July 2023: Concrete works completed;
  • November 2023: Lock flooded;
  • Late 2023: First vessels pass through and the lock enters its trial phase;
  • During the 1st quarter of 2024: Lock officially enters service.      

By keeping the waterway open throughout the works, nearly 7.7 million tonnes of goods passed through the Ampsin-Neuville lock site in 2022.

Click here to download a video, a timelapse and photos of the works to upgrade the Ampsin-Neuville lock site to large-gauge navigation.

CONSTRUCTION SITE OPENS TO THE PUBLIC

As part of Open Construction Sites Day, organised by Embuild, the works to upgrade the Ampsin-Neuville lock site to large-gauge navigation will be exceptionally open to the public. 300 people will have the chance to visit this major construction site. 

Full information at www.journeechantiersouverts.be: Click here to access the registration form.

BACKGROUND 

Located on the Meuse, in the municipalities of Huy and Amay, the Ampsin-Neuville lock site is the last bottleneck on the waterway linking Namur to the seaports of Antwerp and northern Europe. 

The site originally had two locks, which entered service in 1958: a medium-gauge lock (136 x 16 metres, capacity: 2,000 tonnes) and a small-gauge lock (55 x 7.5 metres, capacity: 600 tonnes).

Both locks were smaller than those at the sites upstream and downstream. They therefore needed to be replaced by two new large-gauge locks (225 x 12.5 metres and 225 x 25 metres) to reduce waiting times for boat operators and allow larger vessels to pass.

Work began in summer 2018 and is being carried out in two phases to ensure vessels can continue to pass:

  • Replacing the 55 x 7.5-metre lock with a 225 x 12.5-metre lock (capacity: 4,500 tonnes, equivalent to 280 lorries of 16 tonnes each).
    This first lock officially entered service on 18 January 2022. More information: 220118-ampsin-mise-en-service-ecluse-moyenne-cp.pdf (sofico.org)

    A new control room has also been operational since November 2021.
  • Replacing the 136 x 16-metre lock with a 225 x 25-metre lock (capacity: 9,000 tonnes, equivalent to 560 lorries of 16 tonnes each).
    This is the project’s ultimate objective. The lock is scheduled to enter service during the first quarter of 2024. 

In time, the works will also enhance the setting for users, cyclists and walkers:

  • The N90 has been made safer and its route altered to allow the lock site to be upgraded to large-gauge navigation;
  • The footbridge over the weir and the new lock, linking the municipalities of Amay and Huy, has been undergoing replacement since September 2021. The section of the bridge over the future fish pass was installed in 2022. It will be extended to cross the national road and fitted with access ramps connecting to the existing cycle paths. The footbridge is due to be operational by the end of 2023; 
  • The left bank downstream of the site will be landscaped to give it a more natural character;
  • A new fish pass, in the form of an artificial river, will allow various species to get past the weir and provide spawning areas for some of them. It is due to be operational by the end of 2023. 

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeTransforming infrastructure and territories
  • SubjectNews
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.