News

Major renovation of Namur prison: a question of organisation

Situation avant rénovation.
Situation avant rénovation.

Opened in 1876, Namur prison was built according to the four-wing star-shaped model of the time, to house 134 inmates. Since 2017, the Régie des Bâtiments has been carrying out a major renovation to improve prison conditions and increase capacity to 144 places. After wings B and D were renovated between 2017 and 2019, wings A and C are now receiving a major upgrade. The public contract was awarded to contractor Duchêne.

Each wing has its own accent colour, also used, for example, on the duct casings.

Working in an operational prison is, of course, no easy matter. It calls for rigorous planning and organisation. In this case, wing C was prioritised, and its occupants were transferred to other wings or prisons for the duration of the works. They have now returned to their modernised cells, allowing the contractor to move on to wing A. Renovation work on the panopticon is also under way.

The old walkways were demolished and replaced with wider ones to allow trolleys to pass and make meal distribution easier.
The new metal staircases were designed so that they could be assembled on site, one level at a time.

A major coordination effort

The renovation work focused mainly on external and internal joinery, fixed furniture, building services, and floor, wall and ceiling finishes. Xavier Neyman, site manager at Duchêne: “We work with subcontractors on this project. Once the structural work is complete, including concreting and masonry, the various trades come in: electricians, heating engineers, metalworkers, joiners… Our job is to coordinate everything. We have brought back many of the subcontractors who worked on wings B and& D (editor’s note: Duchêne had already won the public contract to renovate wings B and D, in partnership with BPC).”

After renovation.

Pandemic and shortages

As elsewhere, the pandemic also affected the site. Xavier Neyman: “Fortunately, our subcontractors were able to cope. We only had teams placed in quarantine. We will complete the work within the allotted time (July 2022), although we would have liked to finish earlier. COVID used up our contingency.”

As for the shortage of materials, its main impact has been a sharp rise in prices. “It’s a real financial black hole. Steel, timber… and we don’t know when or where it will stop. Our tender price dates from 2019. Public contracts are thankfully subject to price revision, based on a calculation of wage and material price increases, but this will not cover all the increases we are seeing at present, as they are truly exceptional.”

Good collaboration with the client

The contractor encountered far fewer surprises on wings A and C, having been well prepared by the work previously carried out on the other two wings. Both the Régie des Bâtiments and the contractor learned from the work undertaken between 2017 and 2019. Surveys were carried out following that work, enabling the client to add extra items to the specification so that as many “surprises” as possible could be budgeted for from the outset this time.

Cell doors must meet precise standards for both fire resistance and resistance to forced entry.

But no two wings are the same. Xavier Neyman: “In a building this old, no wall is truly straight, to put it somewhat crudely. This calls for good collaboration with the client. For example, in the psychiatric wing, we found that there wasn’t enough room for the building services, and the tiling was showing its age. We took the opportunity to remove the screed and lay new tiles, although this had not been planned initially. We did so in consultation with the client, as it was obviously easier to integrate the building services into a new screed.” 

Project details

Client
Régie des Bâtiments (for the SPF Justice)
Architect
Régie des Bâtiments
Main contractor
Duchêne (Eiffage Group)

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeRenovating existing buildings
  • SubjectNews
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.