Liège, E25-E40/A602 link: modernisation work on the Cointe Tunnel towards Brussels is on schedule

The final summer phase of the E25-E40/A602 link modernisation project, focusing on the Cointe Tunnel towards Brussels, is currently on schedule. Work requiring the infrastructure to be closed began just over a month ago. SOFICO and its technical partner, SPW Mobilité et Infrastructures, provide an update on progress.
As a reminder, the work is taking place on the left bank of the Meuse, in the longest tunnel on the E25-E40/A602 link, the Cointe Tunnel, and is confined to the bore towards Brussels. Since 30 June, it has required the closure of the link towards Brussels between junction 38, “Angleur/Grosses Battes/Belle-Ile”, and junction 35, “Avroy/Laveu”.

All the equipment was removed during the first 10 days of the closure, allowing the passive fire protection system to be installed. This system underpins the rest of the project and is now more than 90% complete, with only a few more complex areas still to be treated.
Most of the equipment has already been installed, but still needs to be connected, which sometimes involves laying several kilometres of cable. Each item of equipment is tested individually as it is installed. Once this work is complete, integrated tests will be carried out to verify that everything is working properly.

On projects of this kind, operations must be carefully coordinated to ensure everyone’s safety.
BACKGROUND
Since the link opened in June 2000, quarterly maintenance work carried out at night has helped maintain a high level of safety and comfort for users in the Cointe Tunnel and across the rest of the E25-E40/A602 link.
However, after more than 20 years in service, the infrastructure and its many items of equipment needed to be modernised and brought up to standard to maintain this level of service for users. The work therefore had to be scheduled.
Work that could not be carried out while keeping traffic partially open, or by working only at night, was scheduled for the period with the least impact on users: the summer holidays.
This is the third and final summer in which part of this strategic route has had to be closed to traffic to complete the work.
The Cointe Tunnel towards Brussels is scheduled to reopen in just under three weeks, on Monday 26 August at 6 am, in time for the start of the school year.