Liège: E25-E40/A602 link: Cointe tunnel modernisation works towards Luxembourg on schedule

Liège: E25-E40/A602 link: Cointe tunnel modernisation works towards Luxembourg on schedule

Modernisation of the Cointe tunnel towards Luxembourg, which began at the start of the summer holidays, is currently on schedule. Work requiring the infrastructure to be closed began around a month ago, and SOFICO and its technical partner, SPW Mobilité et Infrastructures, have provided an update on progress. 

As a reminder, the work is focused on the left bank of the Meuse, in the longest tunnel on the E25-E40/A602 link, the Cointe tunnel, and is confined to the bore towards Luxembourg. It requires the link to be closed between junction 35, “Avroy-Laveu”, and junction 37, “Val-Benoit/Seraing/Marche”, towards Luxembourg. 

All equipment was dismantled during the first 10 days of the closure, allowing passive fire protection to be installed. This is the key to the remainder of the project. It is now more than 90% complete, with only some more complex areas left to tackle. 

Most of the equipment has already been installed, but still needs to be connected, sometimes requiring kilometres of cable to be laid. Each item of equipment is tested individually as it is installed. Once this is done, integrated tests will be carried out to verify that everything is working properly.   

On a project of this kind, the various operations must be coordinated effectively to ensure everyone’s safety. 

BACKGROUND

Since it opened in June 2000, quarterly maintenance work carried out at night has helped maintain a high level of safety and comfort for users in the Cointe tunnel and across the rest of the E25-E40/A602 link.

However, after more than 20 years in service, the infrastructure and its many items of equipment needed to be modernised and brought up to standard to maintain this quality of service for users. The work therefore had to be planned.

As this work cannot be carried out while keeping traffic partially open or by working only at night, it was scheduled for the period with the least impact on users: the summer holidays. 

The Cointe tunnel towards Luxembourg is due to reopen in just under three weeks, on 28 August at 6H, in time for the start of the school year. 

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectNews
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.