JOSKIN ESA: Luxembourg facility takes shape

After a delayed start, work on JOSKIN ESA’s new plant is now progressing at pace in the Grand Duchy of Luxembourg.
As the site chosen for the project spans two municipalities, Sanem and Esch-sur-Alzette, twice as many building permits had to be obtained. This delayed the start of the project until December 2023, almost a year later than planned.

With the steel frame of the west hall complete and its Hebel panel cladding well advanced, teams are now installing the roof sheets. Insulation and waterproofing work is due to begin in mid-June.
The building work is expected to be completed, with the buildings roofed, enclosed and fitted with floor slabs, by the end of October 2024. Installation of the main equipment, including the surface treatment line, is scheduled to begin in January 2025. The plant is therefore expected to become operational in the 3rd quarter of 2025.

The new site comprises 15 800 m² of built-up area on a 6.2 ha plot, including 1.4 ha of landscaped green space. It will house the assembly of large, monocoque bodies and a range of JOSKIN manure spreaders.
The structural work on the Luxembourg project is being carried out by Ramaekers Construction, a Walloon construction company based in Chimay, which has worked with JOSKIN many times before, including on projects in Soumagne, Poland and France.