News

Infrabel wins European innovation award for the “Franière slab”

Infrabel wins European innovation award for the “Franière slab”

This is the second “RailTech Innovation Award 2021” won by Infrabel in just a few years.

Infrabel’s teams are delighted, proud and honoured to announce that they have just won a European innovation award. At a virtual ceremony, the “RailTech Innovation Awards 2021” recognised a made in Belgium project, never before seen in the European rail sector: the so-called “Franière slab” project on the line between Namur and Charleroi.

Innovations from many European countries competed in the latest edition of the international “RailTech Europe” event, held online because of the health crisis. Infrabel won in the “infrastructure” category, with a jury made up of professionals and experts from both the rail sector and the railway industry.

Each of the 4 categories (infrastructure, rolling stock, digitalisation and public transport) had 3 nominees. Infrabel’s use of a gigantic movable slab to renew a section of track was up against a Dutch track lighting system and a British digital infrastructure inspection system.

The made in Belgium innovation, devised by Infrabel’s Liège-based teams, therefore came out on top. Infrabel had already received a similar award a few years ago for a 3D simulator designed to train staff responsible for safety around worksites.

A movable slab weighing as much as 18 passenger aircraft

Last year in Franière, Infrabel’s teams renewed a section of almost 1 km of track on the Walloon backbone in record time.

To do so, they used a completely innovative technique: a gigantic concrete slab was prefabricated alongside the line, on the site of a former goods yard. Measuring 480 m long and 8 m wide, the slab was fitted with track (2x480 m), ballast (the layer of crushed stone) and 4 sets of points. During an exceptional weekend closure of the line on 5 and 6 September 2020, the entire structure was pushed into its final position, a distance of around 16 metres. It was a challenge for a structure weighing 6100 tonnes, equivalent to 18 fully laden long-haul aircraft!

Developed by Infrabel’s engineers, this approach was a first: until then, no section of infrastructure, or even a railway structure, of such length had ever been pushed into place in Europe. The innovation was primarily driven by the aim of limiting the impact of works on traffic. Using traditional construction methods, a project of this kind would have affected train services for several weeks.

Now recognised with an international award, this technique is expected to be used again at 3 other sites in Wallonia in the coming months.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeTransforming infrastructure and territories
  • SubjectNews
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.