Work on the E420 covered cutting at Frasnes-Lez-Couvin is nearing completion. The infrastructure will be available in its final configuration from Friday evening.

From the evening of Friday 1 October, a second lane will be open in each direction, with the speed limit set at 80 km/h. This marks the completion of this phase and of the entire Couvin motorway bypass!
Allée des Frênes will not reopen immediately.

Background

The construction of this approximately 14-kilometre motorway bypass between Frasnes and Brûly was divided into three phases, only one of which was still under way.

The first section of the E420 motorway was inaugurated and opened to traffic on 17 October 2017. It runs for 4.6 km from Frasnes to Ry de Rome.

The second section, covering 8.1 km between Ry de Rome and Brûly, was inaugurated on 31 August and 1 September 2019, before opening to traffic shortly afterwards on 6 September 2019.

The third phase of the works began on 3 October 2016. It involved building a covered cutting at Frasnes beneath the railway line, a structure approximately 800 metres long, including an 80-metre tunnel. Coming from Charleroi, this underpass is the gateway to the Couvin bypass towards France. 

Since Friday 7 June 2019, traffic has been able to use one lane in each direction through one half of the underpass, with a reduced speed limit.

Since 17 September 2021, both tunnels in the covered cutting have been open simultaneously, each carrying one lane in each direction, with the speed limit set at 50 km/h.

Company appointed through a public tender to carry out phase III:

JAN DE NUL

The total cost of the Couvin motorway bypass project is expected to amount to approximately €180 million excluding VAT, funded by SOFICO with the help of an €80 million repayable loan granted by the EIB.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeTransforming infrastructure and territories
  • SubjectNews
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.