E42/A15: Wanze: spectacular works on the Huccorgne viaduct

E42/A15: Wanze: spectacular works on the Huccorgne viaduct

This morning, the rehabilitation works on the Huccorgne viaduct, which carries the E42/A15 near Wanze, entered a particularly impressive phase: the removal and subsequent installation of the beams on the approach spans. These operations will take place over several days and involve visually spectacular manoeuvres.

In total, during this phase, which is focused on the bridge that normally carries the lanes towards Liège, 36 beams, each weighing 60 tonnes and measuring 30 metres in length, will be handled on the approach spans in lifting operations reaching heights of up to 60 metres. Previously, 4,350 m² of deck had been sawn, demolished and removed, amounting to a total of 1,950 tonnes.

Over the coming weeks and months, 4,350 m² of precast floor slabs will be installed, 180 tonnes of reinforcement will be fabricated and put in place, and more than 650 m² of concrete will be poured.

As for the central section of the viaduct, now an “island” surrounded by a void, the deck has been completely stripped back (with the removal of various fittings and the surfacing), and concrete repairs are due to begin shortly.

A mobile scaffold has been erected on this central section of the viaduct and will allow the necessary repairs to be carried out on the outer and underside faces of the box girder.

Inside the box girders, the prestressing cables are currently being tensioned.

Finally, waterproofing will be installed along the entire length of the bridge at the same time (on the approach sections and central section), followed by the surfacing, road markings and various fittings.

De video laadt pas als je op afspelen klikt.

BACKGROUND

This project, the largest planned in the Liège region in the coming years, involves rehabilitating the Huccorgne viaduct, which carries the E42/A15 motorway near Wanze. In practical terms, the works aim to give the viaduct a new lease of life:

  • Both approach spans will be demolished and rebuilt, with the exception of the piers, which will be retained and repaired;
  • The central section will be rehabilitated;
  • The project also includes installing new waterproofing and surfacing on the viaduct, as well as noise barriers, LED lighting, metal structures to facilitate future inspections (a walkway), and a metal grating between the 2 viaducts,…

For further information: 210622-e42a15-viaduc-de-huccorgne-rehabilitation-lancement-cp.pdf (sofico.org)

One of the project’s biggest challenges is carrying out these substantial works while minimising disruption to road users. The viaduct carries an average of around 60,000 vehicles per day (both directions combined), rising to 2,500 to 3,500 vehicles per hour during peak periods (both directions combined).

To minimise the impact on traffic, 3 major phases (4 months, 6 months, 6 months) have been planned up to July 2023, with the lanes reopened during the second half of 2022:

➢ From 2 August 2021 to 19 November 2021: strengthening the bridge towards Namur to allow 2 lanes of traffic in each direction to be maintained during the next phase (completed).
➢ From 10 January 2022 to 22 July 2022: works are being carried out on the bridge that normally carries the lanes towards Liège;
➢ From 9 January 2023 to 19 July 2023: works will be carried out on the bridge that normally carries the lanes towards Namur.

Throughout the different phases of the project, the general aim is to maintain 2 lanes of traffic in each direction on the motorway, with a maximum speed limit of 50 km/h.

Below the motorway, Rue Robiewez and Rue Famelette have been closed from 2 August 2021 until 2 August 2023. A diversion is in place via the N652/Route de l’Etat, Route de Lavoir and Rue Biénonsart

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeRenovating existing buildings
  • SubjectNews
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.