E42/A15, Wanze: spectacular operations on the Huccorgne viaduct project

Since this morning, the rehabilitation project on the Huccorgne viaduct, which carries the E42/A15 near Wanze, has entered a particularly impressive phase: removing and then installing the beams on the approach spans. These operations will take place over several days and involve visually spectacular manoeuvres.
In total, during this phase, which is focused on the bridge that usually carries traffic towards Liège, on the approach spans, 36 beams, each weighing 60 tonnes and measuring 30 metres long, will be handled in lifting operations reaching heights of up to 60 metres.

Previously, 4,350 m² of deck was sawn, demolished and removed, amounting to a total of 1,950 tonnes.
Over the coming weeks and months, 4,350 m² of precast concrete deck panels will be laid, 180 tonnes of reinforcement steel will be cut, bent and installed, and more than 650 m² of concrete will be poured.


As for the central section of the viaduct, now an “island” surrounded by empty space, the deck has been completely stripped back (with the various fittings and surfacing removed), and concrete repairs are due to begin shortly.
A mobile scaffold has been erected on this central section of the viaduct, enabling the necessary repairs to be carried out on the box girder’s outer and soffit faces.


The prestressing cables inside the box girders are currently being tensioned.
Finally, waterproofing will be installed along the entire length of the bridge at the same time, covering both the approach spans and the central section. This will be followed by surfacing, road markings and various fittings.
BACKGROUND
This project, the largest to be carried out in the Liège region in the coming years, involves rehabilitating the Huccorgne viaduct, which carries the E42/A15 motorway near Wanze. In practical terms, the work will give the viaduct a thorough overhaul:
Both approach spans will be demolished and rebuilt, while the piers will be retained and repaired;
The central section will be rehabilitated;
The project also includes installing new waterproofing and surfacing on the viaduct, as well as noise barriers, LED lighting, metal structures to facilitate future inspections (a walkway), and a metal grating between the 2 viaducts, among other works.
For further information:
210622-e42a15-viaduc-de-huccorgne-rehabilitation-lancement-cp.pdf (sofico.org)
One of the project’s biggest challenges is to carry out this extensive work while causing as little disruption as possible to road users. The viaduct carries an average of around 60,000 vehicles a day (both directions combined), rising to 2,500 to 3,500 vehicles per hour at peak times (both directions combined).


To minimise the impact on traffic, 3 main phases (4 months, 6 months and 6 months) have been scheduled up to July 2023, with the lanes reopening in the second half of 2022:
- From 2 August 2021 to 19 November 2021: strengthening the bridge towards Namur to allow 2 lanes of traffic in each direction to remain open during the following phase (completed).
- From 10 January 2022 to 22 July 2022: work is being carried out on the bridge that usually carries traffic towards Liège;
- From 9 January 2023 to 19 July 2023: work will be carried out on the bridge that usually carries traffic towards Namur.
Throughout the various phases of the project, the general approach is to keep 2 lanes of traffic open in each direction on the motorway, with a maximum speed limit of 50 km/h.
Below the motorway, Rue Robiewez and Rue Famelette have been closed since 2 August 2021 and will remain closed until 2 August 2023. A diversion is in place via the N652/Route de l’Etat, Route de Lavoir and Rue Biénonsart.