E42/A15, Huccorgne viaduct works: Beam replacement on schedule despite windy weather

E42/A15, Huccorgne viaduct works: Beam replacement on schedule despite windy weather

Work to replace the beams on the approach spans of the bridge that normally carries traffic towards Liège is nearing completion as part of the Huccorgne viaduct rehabilitation project (E42/A15). Despite occasionally very windy weather, the visually spectacular lifting operations have remained on schedule.

In total, during this phase focusing on the bridge that normally carries traffic towards Liège, 36 beams, each weighing 60 tonnes and measuring 30 metres long, were handled in lifting operations reaching heights of up to 60 metres.

Thanks to the work of the teams, the replacement was completed to schedule despite occasionally windy weather: in just under a month. Removal of the old beams began on 15 February. The final beams are being installed this Thursday, 10 March.

Each of the new beams is precast in a factory and delivered to the site by abnormal load. Installing them is an important stage, as it will notably allow the bridge’s longitudinal profile to be adjusted and improve comfort for road users. 

Previously, 4,350 m² of deck had been sawn, demolished and removed, a total of 1,950 tonnes.

Over the coming weeks and months, 4,350 m² of precast deck panels will be installed, 180 tonnes of reinforcement will be fabricated and placed, and more than 650 m² of concrete will be poured.

As for the central section of the viaduct, now an “island” surrounded by empty space, the deck has been completely stripped back, with the various fittings and surfacing removed. Since the start of this week, the mobile scaffolding erected on this central section has been carrying out the necessary repairs to the outer and underside faces of the box girder.

Inside the box girders, the prestressing cables are currently being tensioned. 

Finally, waterproofing will be installed along the entire length of the bridge at the same time, on both the approach sections and the central section, followed by surfacing, road markings and various fittings. 

BACKGROUND

This project, the largest to be undertaken in the Liège region in the coming years, involves rehabilitating the Huccorgne viaduct, which carries the E42/A15 motorway at Wanze. The works will give the viaduct a complete overhaul:

  • Both approach spans will be demolished and rebuilt, while the piers will be retained and repaired;
  • The central section will be rehabilitated;
  • The project also includes installing new waterproofing and surfacing on the viaduct, as well as noise barriers, LED lighting, metal structures to facilitate future inspections (a walkway), and a grating between the 2 viaducts,…

For further information:

210622-e42a15-viaduc-de-huccorgne-rehabilitation-lancement-cp.pdf (sofico.org)

One of the project’s biggest challenges is to carry out these extensive works while causing as little disruption as possible to road users. The viaduct carries an average of around 60,000 vehicles a day (both directions combined), rising to 2,500 to 3,500 vehicles per hour at peak times (both directions combined).

To minimise the impact on traffic, 3 major phases (4 months, 6 months, 6 months) have been scheduled up to July 2023, with the lanes reopening in the second half of 2022:

  • From 2 August 2021 to 19 November 2021: strengthening the bridge towards Namur to maintain 2 lanes of traffic in each direction during the next phase (completed). 
  • From 10 January 2022 to 22 July 2022: works on the bridge that normally carries traffic towards Liège;
  • From 9 January 2023 to 19 July 2023: works on the bridge that normally carries traffic towards Namur.

Throughout the various phases of the project, the general aim is to maintain 2 lanes of traffic in each direction on the motorway, with a speed limit of 50 km/h.

Below the motorway, Rue Robiewez and Rue Famelette have been closed from 2 August 2021 until 2 August 2023. A diversion is in place via the N652/Route de l’Etat, Route de Lavoir and Rue Biénonsart.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeRenovating existing buildings
  • SubjectNews
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.