Coronavirus crisis: impact on the progress of road and motorway works

The Coronavirus epidemic and the health measures adopted by the Federal and Walloon Governments have forced private construction companies and the various public services to review their working arrangements. Mobility Minister Philippe HENRY and SOFICO assess the impact of the Coronavirus crisis on the progress of road and motorway works.
“Our priority is to protect staff while ensuring the safety of everyone in work zones. That is why we need a clear assessment of the situation and must prioritise certain tasks, such as monitoring work zone signage,” says Philippe HENRY, Mobility Minister responsible for infrastructure.
SOFICO has also put the necessary arrangements in place for its staff to ensure that all invoices submitted by companies are paid in full and on time, without any disruption.
There are currently 17 worksites on the strategic road network. Five are still suspended because of the winter period and will only resume when weather conditions are favourable.
Of the 12 active worksites, in view of the health measures adopted by the Federal Government in response to the Coronavirus epidemic, several companies have decided to suspend their work (except for monitoring and maintaining work zone signage). The decisions are due to the following reasons:
- Protecting the health of staff working in teams, with several people in vehicles and working in close proximity at site offices, for example
- Difficulties sourcing materials and equipment, particularly from abroad
The duration of these various suspensions has not yet been determined. In most cases, the suspension of work on these sites will inevitably delay the announced completion date, although the extent of the delay cannot yet be assessed.
Other worksites are continuing with significantly reduced activity, in compliance with the health and safety rules required by the Federal Government:
- E42/A8: Construction of a roundabout at exit 35 Blandain/Hertain
- E420/N5: Construction of the Couvin bypass: work due to stop on Friday 27 March
- R9: Construction of a new ring road access and modification of the “Palais des Expositions” exit in Charleroi
- N50: Rehabilitation of the Ghlin crossing
Companies are holding daily meetings to assess how work on the sites can continue. This list may therefore change over the coming days.