A section of the “Brussels-Luxembourg” line re-electrified using technology new to Europe

Nouveau poste d’alimentation de Heisnch – Droits réservés
Nouveau poste d’alimentation de Heisnch – Droits réservés

Following works that required rail traffic to be suspended for 3 weeks (in phases between Libramont and the Luxembourg border), a 66km section of the “Brussels-Namur-Luxembourg” line is about to be fully re-electrified. This upgrade will allow more trains to run, including heavier trains, at higher speeds.

The works, which are nearing completion, involve switching from a 3,000-volt power supply to a 25,000-volt supply. They form part of the modernisation of the “Brussels-Namur-Luwembourg” line. The aim is to cut journey times by 20 minutes through re-electrification works such as those now under way, as well as civil engineering works and the renewal of railway infrastructure (tracks, signalling, etc.). ​

Infrabel and its railway engineering subsidiary TUC RAIL invite you to see the final stages of this re-electrification work and meet the engineers who have achieved this feat using technology that is new to Europe.

The visit will be attended by the Federal Minister for Mobility, the Luxembourg Deputy Prime Minister and Minister for Mobility, and the CEOs of Infrabel and TUC RAIL.

PROGRAMME

  • 10h15: Visit to the facilities at the new 25,000-volt substation;
  • 10h30: Detailed explanation of the works, followed by brief remarks;
  • 10h50: Formal commissioning of the new facilities, with a symbolic gesture;
  • 11h05: Walk to the tracks
  • 11h15: Departure of the “test” train and return to Arlon station, or return by car (see below)

PRACTICAL INFORMATION

There are two options for attending the event:

  • Meet at Infrabel’s CLI: Centre Logistique Infrastructure, next to Arlon station, for a bus journey there and a return trip on the “test train”

Address: Rue des Thermes Romains, 7, 6700 Arlon. Parking on site

or

  • Meet at the new substation in Heinsch (parking on site)

Address: Rue Henri Elsen, 6700 Heinsch. Follow the signposted route from the junction with Route de Neufchâteau

Please wear suitable clothing and footwear for a visit on the tracks. ​

To help us organise the visit, please let us know by return email or telephone whether you will attend and which meeting point you have chosen.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeTransforming infrastructure and territories
  • SubjectNews
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.