A project where everything runs smoothly

As part of the renovation of Namur prison, Erezée-based company Collignon Eng was appointed by main contractor Duchêne (both part of the Eiffage group) to install the electrical systems in the prison area, including the public address system, cell intercoms and CCTV systems. A major project carried out in two main phases since 2018, it is due to be completed in June this year.

This long-term project was carried out in two main phases. The first, covering wings B and D, began in 2018. The second started in 2020 and focused on wings A and C, as well as the psychiatric wing, which is part of wing B. All the work was overseen by the Régie des Bâtiments, which had drawn up highly precise and detailed specifications.

Freddy Houssa, Business Unit Manager at Collignon: “We could have handled the public address, intercom and CCTV work ourselves, but had to work with Engie as a subcontractor. Our role on this part of the project was limited to the cabling, with all the components installed by Engie.”
A new installation in a 19th-century building
As Freddy Houssa explains, Collignon already had some experience with prison facilities, having taken part in the construction of the new prison in Marche-en-Famenne. But the challenges are not necessarily the same when working on a renovation like this one.

The second phase drew on the experience gained during work on the first two wings in phase one, reducing the number of surprises that inevitably arise when working on a building of such age. “

Freddy Houssa: “From one cell to another, whether designed for single, double or triple occupancy, the work is much the same across all four wings. A colour-coded service duct is provided on the walkway for each cell, making it easier to carry out HVAC and electrical work in the cell without affecting the others.”
A substantial project
Even though it was spread over several years, the project represented a significant volume of work for Collignon: around 6,000 hours in phase one and 7,000 in phase two. The teams were not on site continuously, of course, as their work had to be scheduled around the finishing trades. Freddy Houssa: “The challenge on projects like this is that the schedule is always too tight. Fortunately, Collignon’s size and its membership of the Eiffage group give it the flexibility to strengthen the teams when needed.” “
Open collaboration
Like his colleague who followed the project for Duchêne (see article on pages 60-61), Freddy Houssa highlights the excellent working relationship between all the parties involved. Having joined Collignon as a worker in 1979 and worked his way up step by step to finish his career as Business Unit Manager, Freddy Houssa knows from experience that this is not always the case. “Duchêne handled the scheduling and was always open to discussion. Everything went very well. We experienced no significant impact from the pandemic. For phase 2, we placed our orders in advance to limit any potential delays in equipment deliveries. The planning meetings were held in a genuinely open and constructive spirit, which was a real pleasure. I am grateful to the prison’s management, the Régie des Bâtiments and my colleagues at Duchêne.