Anticipating challenges to deliver Paradise
Texte Philippe Selke Photos Philippe Piraux

115 passive-standard apartments across 4 buildings, forming a new mixed-use, green eco-district with other buildings between Tour Paradis and Gare des Guillemins: in a nutshell, that is the project delivered in Liège early last year by the joint venture formed by Besix and its subsidiary Wust. Christian Determe, project manager at Wust, looks back at the challenges overcome to create what has become a highly sought-after place to live.
In 2022, we featured Paradis Express in these pages as a 21st-century station district, bringing together offices, coworking spaces, a hotel with coliving spaces, homes, a nursery, shops and professional services in carefully designed architecture and leafy surroundings. A unique place to live and work, with extensive underground parking and the Tram as an added bonus. While the office and hotel section, built by Besix for Befimmo, was delivered in 2022, the residential section, comprising 4 buildings of varying heights, was completed almost 2 years later. Matexi commissioned the Besix, Wust joint venture to carry out the construction.

On familiar ground
Christian Determe was responsible for managing the joint venture. “Putting the team together was made easier by Besix having already been on site for several years, which meant I could draw on people who knew the site. I was able to rely on people experienced in finishing works, as well as project engineers for technical services and façades, because the Besix group has strong project management expertise across all trades.”
The project was designed as an eco-district, with all homes built to passive standards. The insulation, made of polystyrene, is 28 cm thick on the façades, exceeding regulatory requirements. In addition, each building has a central gas boiler that supplies a hot-water heat exchanger system in every apartment. Although uncommon, this system provides efficient heat distribution.


Anticipating the challenges
The knock-on effects of COVID caused delays in the supply of materials, forcing Wust to order some items several months in advance and store them in external warehouses because of the large quantities involved. The construction work was also complicated by the city-centre location, which limited storage options.
Part of the basement, with the parking slab already built by Besix as an extension of the office section, was used for the site facilities. Two apartments were then rented in the neighbouring Yust hotel to provide site offices and free up storage space on the ground-level slab.

Christian Determe highlights two major challenges: “One of the biggest technical difficulties was maintaining the watertightness of the parking slab we were building on, as it was already equipped and partially in use. Installing the two tower cranes on the slab was another challenge.” Finally, the delayed Tram works nearby caused coordination difficulties, with numerous meetings needed to manage interactions between the two sites as effectively as possible. In short, site organisation came down to one word: anticipation.
This approach proved crucial to meeting the deadlines. Work was carried out on several buildings in parallel, with an extremely tight finishing schedule. This required close coordination between the various subcontractors, who had to move to a different apartment every day and a half. Completing the structural work on the two smaller buildings meant that as many subcontractors as possible could start the finishing work there, while structural work continued on the two tallest buildings. Christian Determe: “At the busiest point on site, we had up to 140 workers on site at the same time. We also increased the site management team accordingly, with no fewer than 10 people dedicated solely to project management, which is unusual. This enabled us to deliver our brief on time.”

Question about this story? Ask your question
Who worked on it
- ClientMatexi
- ArchitectsA2M, Bureau d’architecture Greisch (BAG) et Jaspers & Eyers Architects
- Main contractorSM Besix: Wust
Keep following this
Get an email when a new story is published. No account needed.
- ThemeTransforming infrastructure and territories
- SubjectLiège