New façades for a residential complex in Anderlecht
Texte Joaquim Dupont Photos Franki

The Goujons residential complex in Anderlecht is undergoing a major renovation. In charge of the project alongside Louis De Waele, Liège-based contractor FRANKI is showcasing the breadth of its expertise: building new balconies, insulating façades, installing new timber window frames, ventilation, … All these tasks are being carried out in sometimes challenging working conditions, thanks in particular to excellent collaboration with the parties involved.
New balconies and a busy programme
FRANKI’s teams first set about demolishing the existing balconies, some of which were in a poor state, to make way for new ones, as Frédéric Rolin, site manager for the Goujons project, explains: «First, we cut off the old balconies, more than half of which were unusable. They were also heavily blackened by pollution. We were then able to install the new balconies, before turning to façade insulation and fitting new timber window frames over the old ones».
The contractor then moved on to work inside the building: «We were also responsible for removing the interior window frames before installing new window sills. The wide-ranging programme also includes renovating the bathrooms and their ventilation systems. This project is a perfect opportunity to demonstrate our versatility and expertise across different fields», he adds.

Working safely in an occupied building
As the renovation of Goujons is being carried out in an occupied building, the client’s main requirements were to minimise disruption to residents as far as possible and to comply with safety and evacuation measures throughout the project.
The major works on the outside of the building required a comprehensive safety protocol. The balconies and, in particular, the concrete cornices, 60 cm wide and 30 cm thick, had to be cut off by crane. This work was carried out in three phases so that the necessary safety and protection measures could be put in place. «Each phase began with the installation of Alimak platforms, to prepare for fitting the balcony brackets and attaching a lifeline around the entire building. For most of the project, the workers used harnesses and were attached to the façade via the lifeline», the site manager explains.

Unusual challenges
The contractor also had to contend with a lack of information about the structure of the existing balconies: «We had very few original plans for the building, which was built in 1970. We therefore had to carry out numerous investigations to understand its structure and ensure the support brackets could be fitted safely ahead of the installation of the new balconies». During this work, FRANKI’s teams found that the building was not perfectly straight. The weight of the corner balconies put too much load on the anchor points, slowing down this phase of the works. «In addition, for aesthetic reasons, the design team did not want columns at the corners of the building, which also made the engineers’ work more challenging», he adds.
Flexible partners, successful collaboration
The site manager was keen to highlight the good working relationship between the various project partners, as well as the flexibility of the client, Foyer Anderlechtois, and the two architectural practices, Karbon Architecture and TVK, even when unexpected issues arose: «During the project, two companies involved in the work, including the balcony manufacturer, went bankrupt. This inevitably affected the programme, as we had to find alternatives along the way. Our partners were very understanding about this».
FRANKI carried out the project in a temporary joint venture with contractor Louis De Waele, in a collaboration with a strong human dimension. «There was a good rapport between our teams and between the respective site managers. Likewise, relations between our workers and the residents, which were very difficult at the start of the project, quickly developed into a relationship of mutual respect. This was, of course, a great source of satisfaction for FRANKI», concludes Frédéric Rolin.

Question about this story? Ask your question
Who worked on it
- ClientLe Foyer Anderlechtois
- ArchitectsKarbon Architecture et TVK
- Main contractorsAM Franki: Louis De Waele
Keep following this
Get an email when a new story is published. No account needed.
- ThemeRenovating existing buildings
- SubjectBruxelles