Work begins on Suzan Daniel Bridge

Beliris, the public construction expert for Brussels, begins work on 2 September on the Suzan Daniel Bridge, which will link Simon Bolivar Boulevard to Avenue du Port at the junction with Rue Picard. Designed for public transport, cyclists and pedestrians, it will span the Charleroi-Brussels-Antwerp Canal over a total length of 90 m. A vital missing link between Brussels-North station and Tour et Taxis, this structure will offer passers-by a new perspective on the canal and the future Parc du quai des Matériaux.
A new mobility link
The bridge is a first for Brussels, as it is entirely dedicated to active mobility: public transport users, pedestrians and cyclists will be able to share it harmoniously. It will reconnect neighbourhoods and areas undergoing development. Delivered in partnership with Bruxelles Mobilité, Bruxelles Environnement and the Port de Bruxelles, the bridge will also provide direct access to the future recreational park on Quai des Matériaux, which Beliris will soon redevelop.
A technological challenge
The bridge consists of a main span with a 60 m clear span over the canal, and two side spans with 30 m clear spans over the quays. The concrete bridge deck is suspended from two particularly slender steel arches. The arches and hangers of the main span are made of steel and painted white, while the arches of the side spans are grey concrete. An access ramp has already been built between Quai des Péniches and Quai de Willebroeck in preparation for the bridge installation.

Space for everyone
The bridge will have two circulation areas: a 7 m-wide asphalt area for public transport and a 6 m-wide timber area for cyclists and pedestrians. From the bridge, cyclists and walkers will enjoy unobstructed views of the canal and the future park. To ensure comfort for people with reduced mobility and cyclists, the gradient has been kept below 4% along its entire length.
The bridge maintains a clearance of 7 m across the full width of the canal to allow barges carrying containers to pass. A clearance of 4 m is provided over Quai des Péniches for emergency services.
Natural light
Numerous light wells in the bridge deck, protected by grilles, will allow natural light to reach the quays beneath the bridge. LED lighting on the guardrails will provide functional lighting at night. Architectural lighting, designed in line with the City of Brussels lighting plan, will highlight the arches, hangers and piers beneath the deck.
Schedule and budget
Work on the bridge begins on 2 September and is due to finish in spring 2021. Work on the park on Quai des Matériaux is due to begin in mid-2020. Together, these projects are an impressive example of urban development in the Brussels canal zone. A sum of €6.75 million has been allocated to the project, which is being delivered by Beliris teams, with project designers Greisch and contractor Jan de Nul, Aelterman.
A new name: Suzan Daniel
The bridge’s name was chosen through a participatory process in which members of the public could submit ideas and select a name from five shortlisted proposals. Suzan Daniel received the most votes. Born in Brussels in 1918, Suzan Daniel became involved in Brussels’ gay community at an early age and went on to become one of its leaders. In 1953, she attended a conference on gender equality in Amsterdam. On her return, she was determined to establish Belgium’s first LGBT+ movement. She died in Uccle in 2007.
Question about this story? Ask your question