SPIE modernises Charleroi Airport’s airfield lighting and strengthens the long-term safety of flight operations

SPIE Belgium, a subsidiary of the SPIE Group and Europe’s leading independent multi-technical services provider in the energy and communications sectors, announces the completion of the final phase of a major programme to modernise the lighting system at Charleroi Airport (BSCA). Carried out since 2018 in close collaboration with SOWAER (Société Wallonne des Aéroports), the project is one of the most significant technical projects undertaken at a Walloon airport in recent years.
A strategic project at the heart of airport safety
Essential but largely invisible to the general public, airfield lighting plays a crucial role in the safety of flight operations, guiding aircraft on the ground and during approach and take-off.
“Airfield lighting is at the heart of airport safety. Thanks to this renewal programme, Charleroi Airport now has modern, robust and reliable infrastructure that can support the long-term operation and growth of air traffic,” explains Nicolas Dequeker, Senior Project Manager at SPIE Belgium.
As part of the project, SPIE completely renewed the lighting system’s power supply networks. Nearly 200 kilometres of underground cables were replaced, including primary high-voltage cables (5,000 V), secondary cables (48 V) and earthing cables, as well as several thousand connectors. The next-generation cables installed as part of the project were designed to offer a significantly longer service life, helping to improve the reliability and longevity of the lighting equipment. For this part of the project, SOWAER worked with Câblerie d’Eupen, which specialises in this type of special cable.
Transition to LED: energy efficiency and greater reliability
Charleroi Airport now has an almost entirely LED lighting system, with LEDs accounting for around 95% of all lamps installed. In total, 2,450 lights and 200 signs were replaced with next-generation equipment.
This technological transition delivers:
- an approximately 80 to 85% reduction in the energy consumption of the lighting system,
- energy consumption 5 to 8 times lower than that of the former halogen lamps,
- a service life two to three times longer, together with significantly improved system availability.
Beyond the energy savings, the modernisation has significantly improved operational reliability. Since the circuits concerned were renewed, there have been no technical incidents related to the old cables, which had previously occurred several times a year.
Highly technical works carried out without interrupting operations
One of the project’s main constraints was the specific layout of Charleroi Airport, which has only one runway.
The work was therefore carried out almost entirely at night, during very limited time slots, to ensure the infrastructure was fully operational again each morning for the first commercial flights.
This achievement relied on rigorous organisation, the deployment of highly specialised teams, including a lighting team of 5 to 6 technicians, a project engineer, a draughtsperson and a project manager, with additional staff brought in during cable-pulling phases, as well as temporary technical solutions to ensure operations could continue.
All works carried out for SOWAER are also covered by a five-year warranty, including preventive and corrective maintenance.
“Thanks to this renewal programme, Charleroi Airport now has one of the most reliable lighting systems in its category. We are proud to have helped strengthen the long-term safety and operational performance of the airport,” concludes Nicolas Dequeker.
Key figures
- Share of LED lighting: ~95%
- LED lights and signs installed: 2,650 units
- Total length of cables replaced: ~200 km
- Reduction in energy consumption: ~80 to 85%
- Energy consumption reduced from ~152 kW to ~25 kW
- LED equipment service life: 2 to 3 times longer than halogen
- Estimated service life of high-voltage cables: up to 15 to 20 years
- Technical incidents on renewed circuits: 0 since 2018