Philippeville: N97 to close for a weekend as part of rehabilitation works on the bridge carrying Rue d’Hemptinne

Work to raise and rehabilitate the bridge over the N97 carrying Rue d’Hemptinne in Philippeville is continuing. As announced, the next operations will require the N97 to close for a weekend.
CHANGES TO TRAFFIC CONDITIONS
Under the bridge (N97)
From Saturday 29 November to Sunday 30 November inclusive, traffic on the N97 at the bridge will be completely suspended in both directions. The closure will begin at midnight on Friday night into Saturday and last until midnight on Sunday night into Monday.
This will allow the precast beams and bridge deck slabs to be installed safely.
Diversions will be in place:
- For light vehicles (< 3.5T), via central Philippeville (Rue de Namur, Boulevard de l’Enseignement and Boulevard du Centenaire);
- For heavy goods vehicles (+3.5T), via the N977, N932 and N5.
Depending on weather conditions and the progress of the work, another closure may be scheduled for the weekend of 6 and 7 December or 13 and 14 December.
Once the closure ends, traffic on the N97 will resume on one lane in each direction until 20 December at the latest. A lane may then be temporarily closed again as required by the works.
Above the bridge (Rue d’Hemptinne)
Since August 2025 and for the duration of the works, traffic on the upper section of the bridge, along Rue d’Hemptinne, has been closed in both directions.
A diversion is in place via Chemin de Cocriamont and Rue de l’Arsenal.
Because the road is narrow, traffic on Chemin de Cocriamont is controlled alternately by temporary traffic lights.
Subject to weather conditions, the works are expected to be completed and Rue d’Hemptinne reopened in the second quarter of 2026
BACKGROUND
The works began last August. The following stages are being carried out:
- Demolition of the entire upper section (carriageway, pavements, kerbs, guardrails, bluestone, etc.);
- Demolition of half the bridge to replace the weakened beams;
- Jacking up the bridge to raise the clearance by 25cm, preventing future impacts;
- Installation of new beams and deck slabs to rebuild the bridge structure;
- Construction of new pavements, installation of new waterproofing and a new asphalt surfacing system.
Before the works, the bridge had a minimum clearance of 4.64 metres. However, to reduce the risk of collisions with heavy goods vehicles, which can cause particularly serious damage to the bridge structure, the rehabilitation project is also being used to raise it to a clearance of 4.89 cm metres, gaining 25 cm in height.