Meeting expectations, whatever the job
Texte Philippe Selke Photos CVISUELS

Snow, rain, sites that are difficult to access, … nothing stops Nelles’ teams from doing their job properly. The energy and expertise they have invested in two very different projects that share one thing in common, water, are proof of this. In the territory of Grand-Halleux, Nelles completed the repair of a section of the N68 in less than 70 working days after it subsided following the floods of July 2021. Meanwhile, in the Grand Bois at Burtonville, the contractor is currently laying water supply pipes to secure the water supply to the municipality of Vielsalm.


Efficiency without detours
At Grand-Halleux, the 350 m-long project was located deep in the forest, so Nelles’ roadworks teams first had to clear the area by felling trees and removing earth slips to gain access to the foot of the road embankment that needed stabilising. The second phase involved demolishing the existing road and sorting the materials. In the third phase, around 4,500 m3 of earth was excavated and taken to various treatment centres. This excavated earth was replaced with a free-draining mass, which is what makes this project distinctive. Site manager Raphaël David explains: “The technique used, which caught the attention of SPW, involves rebuilding a retaining wall using galvanised steel mesh filled with around 2,500 m3 of free-draining stone from quarries. The new road could then be constructed in its entirety on top: sub-base, capping layer, base and bituminous surfacing. All that remained was to apply the road markings and install the signs, reopening the road to the great relief of road users, local residents and tourists, who had previously faced a very long detour because this national road was closed.” It is worth noting that Nelles regularly uses metal cages, also known as gabions, to contain stone, whether to stabilise riverbanks or build car parks, as was the case at CHC.
Despite the difficult weather conditions, Nelles met the deadline, reinforcing the teams on site to ensure the project was completed before the construction industry’s annual holiday period. Raphaël David also highlights the constructive spirit of all the parties involved, from the client to the municipality of Vielsalm and its mayor.

All about water mains
In the Grand Bois at Burtonville, a Nelles utilities team is working on a long-term project, which began in the snow in January this year and is scheduled to finish early next year. The work involves laying pipes of various diameters in wide trenches over long distances, connecting large distribution chambers. Site manager Philippe Namotte explains: “We are carrying out this project in collaboration with Serbi, Bodarwé, Trageco and Tegec. The first prefabricated chamber arrived in January and weighed around 65 tonnes. The project required the installation of two pipes with a diameter of 200 and one with a diameter of 150, but from September a new 1.2 km section will be built using pipes with a diameter of 400. In total, the section under construction is around 2 km long. The trenches accommodate several pipes and are around 1.30 m wide and 1.60 m deep.”


Careful planning was needed to ensure access to these hard-to-reach areas via forest roads, firebreaks and private plots consisting mainly of meadows.
The excavation method, removal of earth and storage of materials are among the challenges posed by the project areas, which are often dead ends. Nelles’ team also had to adapt to specific technical requirements, such as protecting the pipes from stray electrical currents. With all the skills required to carry out this type of work, it is the day-to-day organisation that needs to be adapted.
Een zakelijke vraag aan NELLES frères SA? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectInfrastructure
- CompanyNELLES frères SA