From the Francorchamps road through the village to the Water Highway
Texte : Philippe Selke Photos : Nelles, CVISUELS, LEUSTUDIO

Nelles, the Malmedy-based company, puts its expertise to work every day for the benefit of the public. Whether it is easing traffic through the village of Francorchamps or ensuring the water supply for people in the south of Wallonia, Nelles’ teams are hard at work! Site managers Thomas Bastin and Jean Nelles each introduce a project they are currently supervising

Work to upgrade the road through the centre of Francorchamps began in mid-March, on behalf of SPW and AIDE. It will cover 1.2 km between the “Trou Hennet” and “La Source” roundabouts, with the aim of giving less space to vehicles and more to pedestrians and cyclists. Scheduled for completion in summer 2025, the work is being carried out as a temporary association with Roger Gehlen SA. It will involve a complete reconstruction of the road (sub-base, base course and surfacing) to create two traffic lanes, some on-street parking spaces, pavements on both sides and a two-way cycle lane on one side of the road. Site manager Jean Nelles said: “We are currently working beneath the future Bruyères roundabout, where we are installing a 90 cm-diameter reinforced concrete sewer at a depth of 6 m! Working safely at such depths calls for a specific working method and suitable equipment.”

A busy summer
Jean Nelles said: “We are used to this kind of work, but the main challenge on this project is to stick to the work phases planned around the major events held at the Spa-Francorchamps circuit. These began with the Belgian round of the WEC (World Endurance Championship), held in May, followed by the 24 Hours of GT racing at the end of June and then the Formula 1 GP in July. We are therefore in the most critical phase, and it will only be towards the end of the summer that the schedule will give us a little more breathing space. We are currently on schedule and starting phase 2 of the drainage work, which began on 13 May.”
Other major constraints include the presence of springs, which require continuous pumping, and the need to manage the underground networks belonging to the various utility companies.

Drinking water, a precious resource to share
In Bierset, Thomas Bastin is working on a very different project. Known as “L’Autoroute de l’eau”, it has also been described as SWDE’s project of the century. Nelles has been awarded a section in the municipality of Bierset, in association with Lejeune. Thomas Bastin said: “The project involves installing an 800-diameter water main from the outskirts of Bierset Airport towards Saint-Georges. Our section runs for 2.5 km beneath the road, while our partner Lejeune is laying 3 km across fields.”

The section completed by Nelles follows a straight road with roundabouts, beneath which the pipes were laid at an average depth of 3.5 m, and in some places as deep as 6 m. Thomas Bastin said: “What is a first for us is the length of the pipes: 13.5 m, weighing around 3 tonnes each. This called for technical expertise in the design of the trench supports, as well as great care to keep workers safe while handling these giants. We are now finishing the work by laying the asphalt surfacing and will be well within the schedule, despite the winter weather we experienced.”
About halfway through the project, a pressure test at 17 bar required 700 m3 of mains water… and around a fortnight to fill the pipeline!
In short, this project is unprecedented in scale compared with the conventional drainage work that Nelles also carries out for residential and non-residential buildings.

Experience, not routine
What these two major projects demonstrate is Nelles’ ability to apply its experience with equal energy to projects of every type and scale, in the fields in which the Malmedy-based company specialises.
Een zakelijke vraag aan NELLES frères SA? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeTransforming infrastructure and territories
- SubjectInfrastructure
- CompanyNELLES frères SA