E420/N5: Couvin motorway bypass: underpass beneath the railway opens

From late afternoon on Friday 7 June, traffic will be able to use the half-underpass beneath the railway at Frasnes-lez-Couvin, with one lane in each direction. It provides a direct link between the N5 and the 4.6 km section of the E420 between Frasnes and the Ry de Rome, which opened to traffic in October 2017.

Road users are asked to be particularly attentive and vigilant during the traffic switch, which will take place in several successive stages. Police will be on hand throughout the day to oversee the switch.
The third phase of the Couvin motorway bypass (E420) project involves building a structure approximately 800 metres long, including an 80-metre tunnel, to take the E420/N5 beneath the railway. For traffic coming from Charleroi, this underpass is the gateway to the Couvin bypass towards France.
Work will then focus on completing the other half of the underpass, which is expected to open during the second half of 2020, with two lanes in each direction.
Situation from 7 June (image)
Reminder
Phase 1: Frasnes to the Ry de Rome:
Phase 1, comprising the construction of the twin-barrel Eau Noire culvert and the approximately 4.6 km section between Frasnes and the Ry de Rome, was inaugurated and fully opened to traffic in mid-October 2017. The four roundabouts built along this section had already been in use since mid-2016. It is estimated that the bypass prevents 200,000 lorries from travelling through the centre of Couvin each year.

Phase 2: Ry de Rome to Brûly (French border):
The second phase covers construction of the longest section of the bypass, an 8.1-kilometre stretch between the Ry de Rome and Brûly on the French border. Road markings still need to be applied, safety equipment installed and lighting fitted at the interchanges.
This section of motorway is due to open to traffic during the first week of September, following an opening-weekend celebration on Saturday 31 August and Sunday 1st September. SOFICO wishes to involve local stakeholders (https://sofico.org/autoroute-e420-en-fete-appel-a-candidatures/).

The four phases of the Couvin bypass

- Phase 1a: construction of the twin-barrel Eau Noire culvert (completed from October 2011 to September 2012).
- Phase 1b: construction of the section from Frasnes to the Ry de Rome (from November 2013 to mid-October 2017).
- Phase 2: construction of the section from the Ry de Rome to Brûly (from August 2015 to September 2019).
- Phase 3: construction of the underpass beneath the SNCB railway at Frasnes (from October 2016 to the second half of 2020, BUT partial opening in mid-2019).
- Phase 4: installation of electromechanical equipment (lighting, etc.). This phase will be carried out simultaneously on the various sections concerned.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeTransforming infrastructure and territories
- SubjectInfrastructure